Neustadt Community Expansion Project

Enbridge Gas Inc.
EB-2023-0261

Enbridge Gas Inc. has applied to construct natural gas pipelines in the community of Neustadt, within the Municipality of West Grey.

Enbridge Gas Inc. (the applicant) has applied for approval of/to:

  • Construct pipelines to supply natural gas to approximately 230 new customers in the community of Neustadt, within the Municipality of West Grey, who currently do not have access to natural gas service.
  • Install approximately 4.8 km of 2-inch polyethylene (PE) natural gas distribution pipeline and approximately 7.6 km of 6-inch PE natural gas pipeline, consisting of approximately 6.7 km of supply lateral and 0.9 km of reinforcement pipeline. Enbridge Gas Inc. also proposes to construct ancillary facilities.
  • The form of agreement it offers to landowners to use their land for routing or construction of the proposed pipelines.
  • Charge the OEB-approved System Expansion Surcharge to all new customers that will be taking service from the project. Enbridge Gas Inc. indicates that the project was approved to receive funding assistance under Phase 2 of the Government of Ontario’s Natural Gas Expansion Program on June 9, 2021.

If you would like to request intervenor status for this application, you can do so by completing the Intervenor Form.

Type
Leave to construct
The above links will take you to our document repository

Submit a letter of comment

You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment will be accepted until the record of the proceeding is closed (which usually occurs with the filing of the applicant’s final reply argument). However, you are encouraged to submit your letter as early in the process as you can. Depending on timing of receipt of letters of comment, the applicant will typically provide a respond to the issues raised in those letters. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.

More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters will be placed on our website. Before the letter of comment is placed on the public record, personal contact information contained in the address, phone number, and email address fields of this form is removed. The individual's name and the content of the letter will become part of the public record.

If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your personal contact information. The OEB removes your personal contact information from your letter for privacy reasons before it is posted to our website.

Add Your Letter of Comment

All information provided in this field will be made publicly available and placed on the OEB website. Please do not include any personal contact information in this section.
Upload an attachment only if you need to submit additional information relating to your comment. Only PDF and Word files will be accepted. All information provided in the document you attach will be made publicly available and placed on the OEB website. Please do not include any personal contact information in your attached document.
Choose file
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Get updates about this application:

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Or mail the below address with the reference number EB-2023-0261

Ontario Energy Board
P.O. Box 2319
2300 Yonge Street, 27th Floor
Toronto ON M4P 1E4
Attn: Registrar