Bobcaygeon Community Expansion Project

Enbridge Gas Inc.
EB-2022-0111

Enbridge Gas Inc. has applied to the Ontario Energy Board for approval to construct the Bobcaygeon Community Expansion Project which involves the construction of:

(i) A Supply Lateral, through the City of Kawartha Lakes to Bobcaygeon consisting of:

  • 25 kilometres of 6-inch extra high pressure steel natural gas distribution pipeline
  • 2 kilometres of 6-inch high pressure polyethylene natural gas distribution pipeline
  • 1 kilometre of 6-inch high pressure steel natural gas distribution pipeline

(ii) An Eastern Reinforcement Pipeline, running from Enbridge Gas’s existing system within the Township of Cavan-Monaghan into the City of Kawartha Lakes, comprising 8 km of 6-inch extra high pressure steel natural gas distribution pipeline.

Enbridge Gas Inc. filed its original application with the Ontario Energy Board in May 2022. The original application was placed in abeyance by the Ontario Energy Board pending an update of the evidence by Enbridge Gas Inc. It is important to review the updated application carefully to determine if you will be affected by the changes.

Enbridge Gas Inc. is also asking the Ontario Energy Board to approve the form of agreement that it has offered or will offer to landowners affected by the routing or location of the proposed pipelines.

Enbridge Gas Inc. states that the pipelines are needed to supply natural gas to approximately 3,700 new customers in the community of the City of Kawartha Lakes (including Bobcaygeon) who currently do not have access to natural gas service. Enbridge Gas Inc. states that it intends to charge the OEB-approved System Expansion Surcharge to all new customers that will be taking service from the project.

Enbridge Gas Inc. states that on June 9, 2021, the proposed project (also referred to as the Bobcaygeon Community Expansion Project), was approved to receive funding assistance under Phase 2 of the Government of Ontario’s Natural Gas Expansion Program.

Please review the application for more information about the proposed project.

If you would like to request intervenor status for this application, you can do so by completing the Intervenor Form.

Type
Leave to construct
The above links will take you to our document repository

Submit a letter of comment

You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment will be accepted until the record of the proceeding is closed (which usually occurs with the filing of the applicant’s final reply argument). However, you are encouraged to submit your letter as early in the process as you can. Depending on timing of receipt of letters of comment, the applicant will typically provide a respond to the issues raised in those letters. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.

More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters will be placed on our website. Before the letter of comment is placed on the public record, personal contact information contained in the address, phone number, and email address fields of this form is removed. The individual's name and the content of the letter will become part of the public record.

If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your personal contact information. The OEB removes your personal contact information from your letter for privacy reasons before it is posted to our website.

Add Your Letter of Comment

All information provided in this field will be made publicly available and placed on the OEB website. Please do not include any personal contact information in this section.
Upload an attachment only if you need to submit additional information relating to your comment. Only PDF and Word files will be accepted. All information provided in the document you attach will be made publicly available and placed on the OEB website. Please do not include any personal contact information in your attached document.
Choose file
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Get updates about this application:

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Or mail the below address with the reference number EB-2022-0111

Ontario Energy Board
P.O. Box 2319
2300 Yonge Street, 27th Floor
Toronto ON M4P 1E4
Attn: Registrar