Enbridge Gas Inc. Ridge Landfill RNG Project

Enbridge Gas Inc.
EB-2022-0203

Enbridge Gas Inc. has applied to the Ontario Energy Board for approval to construct approximately 5.7 kilometres of 4-inch diameter extra high pressure steel pipeline, in Blenheim, in the Municipality of Chatham Kent. The proposed pipeline will transport renewable natural gas produced at Waste Connections of Canada Inc.’s planned renewable natural gas facility at Ridge Landfill and connect to Enbridge Gas Inc.’s natural gas distribution system. Enbridge Gas Inc. also plans to construct a renewable natural gas injection station at Ridge Landfill.

Enbridge Gas Inc. states that Waste Connections of Canada Inc. plans to build and operate renewable natural gas gathering, upgrading and compression facilities at Ridge Landfill, a waste disposal facility, in Blenheim. The new renewable natural gas facility will produce and convert landfill gas into renewable natural gas, suitable for injection into Enbridge Gas Inc.’s distribution system. Enbridge Gas Inc. states that Waste Connections of Canada Inc. will pay for the project and that it will have no cost impact on existing ratepayers.

Enbridge Gas Inc. has also applied for approval of the forms of agreements that it has offered or will offer to landowners affected by the routing or location of the proposed pipeline.

Type
Leave to construct
The above links will take you to our document repository

Submit a letter of comment

You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment must be received by the OEB no later than 60 days after the publication or service date of the notice for the application. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.

More about commenting and privacy

More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters can be seen at our offices and will be placed on our website. Before the letter of comment is placed on the public record, all personal (i.e. not business) contact information is removed, such as the individual's address, fax and phone numbers, and email address. The individual's name and the content of the letter will become part of the public record..

If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your contact information. The OEB removes your contact information from your letter for privacy reasons before it is posted to our website.Show less

This information will be visible on the OEB's public website.
Upload an attachment only if you need to submit additional information relating to your comment. Only PDF and Word files will be accepted.
Choose file
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Get updates about this application:

Or mail the below address with the reference number EB-2022-0203

Ontario Energy Board
P.O. Box 2319
2300 Yonge Street, 27th Floor
Toronto ON M4P 1E4
Attn: Registrar