1 1 RP-2000-0068 2 THE ONTARIO ENERGY BOARD 3 4 IN THE MATTER OF the Ontario Energy Board Act, S.O. 5 1998, c. 15, Schedule B; 6 7 AND IN THE MATTER OF an Application by Hydro One 8 Networks Inc. for an order or orders granting leave to 9 construct an electricity transmission line from the 10 Hawthorne Transmission Station to Gamble Junction and to 11 the Ontario-Qu‚bec provincial border at the Ottawa 12 River, all in the regional Municipality of 13 Ottawa-Carleton. 14 15 16 B E F O R E : 17 S.K. HALLADAY Presiding Member 18 K. McCANN Member 19 A. BIRCHENOUGH Member 20 21 Hearing held at: 22 2300 Yonge Street, 25th Floor, Hearing Room No. 1 23 Toronto, Ontario on Wednesday, November 22, 2000, 24 commencing at 0940 25 26 HEARING 27 28 VOLUME 1 2 1 APPEARANCES 2 PATRICK MORAN Counsel to Board Staff 3 KATHI LITT/ 4 NABIH MIKHAIL/ 5 ZORA CRNOJACKI 6 7 MARY ANNE ALDRED Hydro One Networks Inc. 8 PETER THOMPSON City of Cumberland 9 MURRAY KLIPPENSTEIN/ Pollution Probe 10 JACK GIBBONS 11 ERNEST McARTHUR Regional Municipality of 12 Ottawa-Carleton 13 PETER BUDD/ TransEnergie, a Division of 14 KRISTIE SEBALJ/ Hydro Quebec 15 DENIS GAGNON 16 LLOYD GREENSPOON Northwatch 17 DAVID BROWN Independent Electricity Market 18 Operator (IMO) 19 20 21 22 23 24 25 26 27 28 3 1 Toronto, Ontario 2 --- Upon commencing on Tuesday, November 22, 2000 3 at 0940 4 THE PRESIDING MEMBER: Please be seated. Good 5 morning. 6 The Board is sitting to hear an application by 7 Hydro One Networks Inc. for an order or orders granting 8 leave to construct an electricity transmission line from 9 the Hawthorne Transmission Station to Gamble Junction 10 and to the Ontario-Quebec provincial border at the 11 Ottawa River, all in the Regional Municipality of 12 Ottawa-Carleton. 13 My name is Sheila Halladay. With me today are 14 Art Birchenough and Ken McCann. 15 May I have appearances, please? 16 MS ALDRED: Good morning. My name is Mary 17 Anne Aldred, spelled A-L-D-R-E-D. 18 THE PRESIDING MEMBER: Ms Aldred. 19 MR. THOMPSON: Yes. My name is Peter Thompson 20 and I am here as counsel for Vice & Hunter, who are the 21 solicitors for the City of Cumberland. 22 THE PRESIDING MEMBER: Mr. Thompson. 23 MR. KLIPPENSTEIN: Good morning, Madam Chair 24 and members of the panel. My name is Murray 25 Klippenstein, counsel to Pollution Probe. 26 THE PRESIDING MEMBER: Mr. Klippenstein. 27 MR. McARTHUR: Good morning, Madam Chair. My 28 name is McArthur, M-c-A-R-T-H-U-R, first name Ernest. I 4 1 appear on behalf of the Regional Municipality of 2 Ottawa-Carleton. 3 THE PRESIDING MEMBER: Good morning, 4 Mr. McArthur. 5 MR. BUDD: Good morning, Madam Chair, members 6 of the Board. My name is Peter Budd. With me is 7 Kristie Sebalj, S-E-B-A-L-J. We represent TransEnergie, 8 a Division of Hydro Quebec. Also with me is Denis 9 Gagnon. 10 MR. GREENSPOON: My name is Lloyd Greenspoon 11 and I am here for Northwatch. 12 THE PRESIDING MEMBER: Mr. Greenspoon. 13 MR. BROWN: Madam Chair, David Brown for the 14 Independent Electricity Market Operator. 15 THE PRESIDING MEMBER: Mr. Brown. 16 MR. MORAN: Madam Chair, Pat Moran, counsel to 17 the Board. 18 I have been asked to put in a couple of 19 appearances for some other people. 20 Richard Stephenson for the Power Workers Union 21 and Michael Janigan for the Vulnerable Energy Consumers 22 Coalition. 23 THE PRESIDING MEMBER: Good morning, 24 Mr. Moran. 25 Any other appearances? 26 Before we begin I would like to make a few 27 preliminary remarks. 28 This is only the second case the Board has 5 1 heard under section 92 of the Ontario Energy Board Act 2 and it is the first application brought by Hydro One 3 Networks. 4 On November 6, 2000, the City of Cumberland 5 wrote to the Board advising that it intended to 6 challenge the legality of Ontario Regulation 365/00 7 insofar as it limits the Board's jurisdiction to decide 8 matters in the public interest. 9 On November 9, 2000, Pollution Probe wrote to 10 the Board indicating its intention to bring a motion to 11 dismiss Hydro One Networks application. 12 The jurisdiction of the Board to deal with the 13 issues raised by Pollution Probe is also tied to the 14 validity of Ontario Regulation 365/00. 15 On November 10, the Board wrote to the parties 16 indicating that it was considering three options for 17 dealing with the issue, and the parties were given the 18 opportunity to make submissions. Needless to say, you 19 are disparate group and no two parties made the same 20 submissions. 21 On November 20, last Monday, a meeting of the 22 full Board was held. At that meeting, the Board decided 23 to state a case on the validity of Regulation 365/00 to 24 the Divisional Court pursuant to section 32 of the 25 Ontario Energy Board Act. 26 As a result of that Board decision, the panel 27 in this case will not be hearing arguments on the 28 validity of the regulation, either by way of preliminary 6 1 motion or in final argument. 2 However, in order to expedite this 3 application, I understand that the parties have agreed 4 that the Board will proceed to hear the evidence in this 5 case on the basis that the regulation would not apply. 6 This will enable the Board to have a full record in this 7 proceeding. 8 The court will deal with the validity of the 9 regulation and the Board will deal with the merits of 10 the application. 11 I would like to stress that this approach in 12 no way prejudices the positions of the parties with 13 respect to the stated case and the validity of the 14 regulation. 15 The Board feels that this approach is a 16 pragmatic one that addresses Hydro One Networks concern 17 on the timing of the application, as well as the 18 intervenors concern with respect to the validity of the 19 regulation. 20 Are there any questions? 21 Before we proceed, are there any preliminary 22 matters? 23 PRELIMINARY MATTERS 24 MR. MORAN: Madam Chair, I have just noted 25 that the on-air light isn't switched on. 26 Thank you. 27 THE PRESIDING MEMBER: Thank you. 28 There are no preliminary matters? 7 Preliminary Matters 1 MR. THOMPSON: Madam Chair, I don't know if it 2 is appropriate to raise it now, but I had raised with 3 Mr. Moran the possibility of scheduling the Cumberland 4 witnesses for time fixed and the time that was suggested 5 to me was Friday at 9:30. I just wanted to put that on 6 the record and if the Board has any concerns with that 7 perhaps they could let me know, otherwise my client is 8 to have my witnesses here at that time. 9 THE PRESIDING MEMBER: The Board doesn't have 10 any concerns with that. 11 Ms Aldred, do you have any concerns with that? 12 MS ALDRED: My only concern would be that I 13 would like to be, obviously, through our case by then. 14 We have anticipated three panels and I'm not sure that 15 that third panel would be through by that time. But, 16 other than that, fine. 17 THE PRESIDING MEMBER: We have planned three 18 days for this hearing. Hopefully, I'm sure we will get 19 to the intervenor evidence on the third day, at least 20 some time, Mr. Thompson. So that would be fine as far 21 as scheduling them for Friday. 22 Mr. Klippenstein, do you have a preliminary 23 motion or have you decided to drop that one? 24 MOTION 25 MR. KLIPPENSTEIN: I was going to say that 26 there was that request outstanding and I'm not sure if 27 the Board had plans on that. I would hope that we would 28 be able to hear it this morning prior to the rest of the 8 MOTION (Klippenstein) 1 hearing. 2 THE PRESIDING MEMBER: Mr. Klippenstein, you 3 have three minutes to convince me why we should dismiss 4 this application. 5 MR. KLIPPENSTEIN: The motion brought by 6 Pollution Probe, Madam Chair, has two basic ideas 7 involved with it. One is that the Board can look at the 8 evidence now, which is in its fullest and most complete 9 form right now from Hydro One, and can say, even in a 10 best case scenario, "This isn't adequate for a 11 decision." In my submission, the obvious question 12 arises, obviously: Well, why shouldn't the Board just 13 hear the evidence? 14 I have given four reasons in the motion 15 materials and they are centering on the fact that if 16 Hydro proposes to add any significant evidence during 17 the hearing now, that would be very problematic. 18 First of all, it would be last-minute surprise 19 evidence. So from the Board Member perspective, it 20 wouldn't have the benefit of being tested by the 21 parties. So it would be inferior evidence arising from 22 the fact that it comes at the last minute. That is 23 problematic because some of the evidence is very, very 24 complicated. 25 So in terms of the quality of the Board's 26 information, last minute evidence, in my submission, 27 would be a major problem. 28 There are also questions of fairness to the 9 MOTION (Klippenstein) 1 parties, the fact that it would contradict the Board's 2 detailed prehearing procedure. So there are real 3 problems if the Board is assuming that it is okay to add 4 significant evidence at the last minute. 5 I have stated that in my motion and I will 6 move to my next point. 7 The next point is one of substance. That is 8 that there appears to be what may well be an extremely 9 problematic problem or gap or contradiction in the 10 evidence right now. 11 As my motion materials say, the question of 12 whether some of the power that is going to go through 13 this new transmission line is going to end up in Quebec 14 and then in the eastern States is a fundamental one. 15 The Board has hints of it in the evidence at 16 this stage. In fact, if one looks at the statements of 17 Hydro Quebec that we filed, Hydro Quebec is saying that 18 they intend to make money through arbitrage -- and they 19 use the term "very profitable" -- by selling power to 20 the eastern States, such as New York, where there is a 21 large price difference. 22 So, in my submission, what we have here is a 23 potentially huge problem for the consumers of Ontario 24 which, to put it bluntly, involves the sale of cheap 25 Ontario power to the eastern New York States at a large 26 profit by Hydro Quebec using the storage facilities of 27 their reservoir. 28 So this is something that is not contemplated 10 MOTION (Klippenstein) 1 by the evidence. If Pollution Probe's understanding of 2 the evidence is correct, it is going to have to be dealt 3 with somehow. 4 This gets back to my first point. If we are 5 going to be, in the middle of a hearing, dealing with 6 some major, major criticisms on some of the economic 7 evidence, how is a Pollution Probe and, more 8 importantly, how is the Board supposed to deal with that 9 at the last minute? This may be, if Pollution Probe is 10 correct, the Churchill Falls of Ontario, in which this 11 facility ends up benefiting Hydro Quebec hugely for many 12 years to come -- and I have nothing against Hydro 13 Quebec -- but at the expense of Ontario consumers. 14 Finally, I would notice that although 15 Pollution Probe has been raising this specific issue 16 repeatedly in the interrogatory period for some weeks 17 now, and that is in some of the letters we received, 18 finally, a partially updated interrogatory response 19 yesterday which says that the assumption in the evidence 20 is that Hydro Quebec will import exactly as much power 21 from Ontario through this transmission line as it will 22 export to Ontario. The numbers are exactly the same. 23 There is no net difference. 24 The implications, in my submission, are 25 momentous for the evidence, because that means that the 26 whole case seems to be assuming that there will be no 27 net export of Ontario power to the northeastern States 28 which are willing to pay a lot for it through Quebec. 11 MOTION (Klippenstein) 1 It is important that this is a two-stage scenario we are 2 concerned about, Ontario to Quebec, Quebec to U.S. 3 jurisdictions. We are not talking about direct Ontario 4 to U.S. 5 But the numbers we received yesterday 6 suggest -- they don't suggest, they state that this 7 whole evidence assumes that all Ontario power that goes 8 to Hydro Quebec comes back. In my submission, that 9 flies against ordinary economic logic. It flies against 10 the evidence, because the evidence itself says Hydro 11 Quebec will try to maximize this transmission line in 12 its own benefit. 13 Furthermore, it flies in the face of the 14 public statement of Hydro Quebec that says: We are 15 going to make a lot of money selling -- storing power 16 and then selling it to New York and others. 17 So we have, in my submission -- I will wrap-up 18 now -- this enormous contradiction between the 19 assumption that there will be no net outflow of power 20 and the reality that is staring at us from several 21 different angles. In my submission, the potential there 22 for of huge amounts of cheap Ontario power to go to 23 Quebec, then to be sold at a large mark-up to 24 northeastern States by Quebec, and the net result will 25 be an increase in Ontario prices. 26 That possibility simply does not appear in the 27 evidence at all. So my concern is, if this is raised in 28 the middle of a hearing the Board will simply not be 12 MOTION (Klippenstein) 1 able to get enough evidence at the last minute to deal 2 with what may be Ontario's Churchill Falls. 3 Thank you. Those are my compressed 4 submissions. 5 THE PRESIDING MEMBER: Thank you, 6 Mr. Klippenstein. 7 --- Off record discussion 8 DECISION 9 THE PRESIDING MEMBER: Thank you, 10 Mr. Klippenstein. 11 We have considered your motion. 12 The panel would like to point out that this is 13 Hydro One's application and Hydro One has the onus of 14 proving to the Board and providing the Board with 15 sufficient evidence to consider the application. The 16 hearing and the testing of Hydro One's evidence is the 17 subject of this oral hearing. 18 But you are free to argue in final argument 19 that Hydro One has not met this onus, either by not 20 providing the Board with sufficient evidence or by 21 questioning the credibility of that evidence in your 22 final arguments and submissions. 23 Therefore, the motion to dismiss this 24 application at this time is dismissed. 25 Are there any other preliminary matters? 26 Ms Aldred. 27 PRELIMINARY MATTERS 28 MS ALDRED: Thank you very much. 13 Preliminary Matters 1 Just before we start I do have some 2 housekeeping matters and some filings that I would like 3 to take care of, several matters that I would just like 4 to file with the Board. 5 The first is the supplementary responses to 6 questions asked by Pollution Probe. These were faxed to 7 all of the parties, but I think they do need to be filed 8 with the Board. 9 Mr. Marritt will be bringing those up. There 10 are also copies on the side. Excuse me, I should have 11 mentioned that. 12 MR. MORAN: Madam Chairman, that can be 13 Exhibit 14.1, Supplementary Interrogatories filed by 14 Hydro One. 15 THE PRESIDING MEMBER: Thank you. 16 EXHIBIT NO. 14.1: Supplementary 17 Interrogatories filed by Hydro One 18 MS ALDRED: The second item would be the 19 supplementary response to Pollution Probe Interrogatory 20 No. 4, which was the evidence that Mr. Klippenstein 21 referred to in his motion. I would like to file that 22 with the Board. 23 THE PRESIDING MEMBER: Thank you. 24 MR. MORAN: Exhibit No. 14.2. 25 THE PRESIDING MEMBER: Mr. Moran, that can 26 probably be just a revised answer to the interrogatory, 27 rather than a specific exhibit. 28 MS ALDRED: The next item is a matter that was 14 Preliminary Matters 1 sent by Hydro One Networks in response to complement 2 evidence. It was sent to all intervenors. 3 MR. MORAN: Exhibit No. 14.2, Madam Chair. 4 MS ALDRED: Excuse me, I'm very sorry, it has 5 already been marked as an exhibit. Mr. Marritt just 6 pointed that out to me. 7 The next item are the CVs. 8 THE PRESIDING MEMBER: I'm sorry, Ms Aldred 9 which exhibit is it? 10 MS ALDRED: It is -- 11 MR. MORAN: It is 13.21. It is already 12 marked. 13 MS ALDRED: It's 13.21, yes. 14 The next item is a group of curriculum vitae 15 of the various witnesses which Hydro will be producing. 16 MR. MORAN: I think we can finally use that 17 Exhibit 14.2, Madam Chair. 18 EXHIBIT NO. 14.2: Curriculum vitae of 19 Hydro One's witnesses 20 MS ALDRED: The next item is a witness 21 responsibility summary which has been served on all the 22 parties, an extra copy is at the side, and which 23 Mr. Thompson shows me is currently Exhibit 13.22. 24 THE PRESIDING MEMBER: Thank you. 25 MS ALDRED: You are ahead of me. 26 The next item for filing is a response to OEB 27 Staff Question 40. It should have been filed before and 28 we are filing it now. 15 Preliminary Matters 1 THE PRESIDING MEMBER: That is the response to 2 the Board Staff Interrogatory. 3 MR. MORAN: Yes. 4 MS ALDRED: Fine. 5 Finally, there is an update to Exhibit B, 6 Tab 4, Schedule 2. Page 104 has been altered, and 7 page 304. 8 That will be dealt with in Panel 2, but I 9 thought I would file it now. 10 THE PRESIDING MEMBER: Thank you. 11 OPENING STATEMENT 12 MS ALDRED: Those are all of the preliminary 13 filings that I wanted to make. 14 I did have a very brief opening statement, and 15 then I will proceed to call my first panel of witnesses. 16 Madam Chair and Members of the Board, as you 17 are aware, this is an application pursuant to section 92 18 of the OEB Act for leave to construct a new 1250 19 megawatt interconnection with Hydro Quebec. 20 The proposal for this interconnection has been 21 developed in concert with Hydro Quebec and will provide 22 substantial benefits to Ontario consumers. 23 As you will hear in the evidence, and as you 24 have read in the prefiled evidence, the proposed 25 interconnection will introduce 1250 megawatts of new, 26 lower-cost generation into the Ontario market and, if 27 approved, will contribute toward the requirement in 28 Hydro One Networks transitional transmission licence to 16 Opening Statement (Aldred) 1 increase interconnection capacity by 2000 megawatts 2 within three years of the opening of the Ontario market. 3 Networks, as we will refer to ourselves during 4 the course of the hearing, is a transmission company. 5 Therefore, in order to assess the benefit to Ontario 6 consumers of the new interconnection, PHB Hagler and 7 Bailly was retained to model the market and render an 8 opinion on the possible benefits to Ontario consumers of 9 the interconnection. 10 PHB Hagler and Bailly, or PA Consulting, as 11 they are now known, will tell you that the 12 interconnection will have a very positive effect on 13 energy prices in Ontario and that the project is 14 decisively economic. 15 As we know, the Board is guided by legislation 16 to approve this project if it finds it to be in the 17 public interest. 18 In preparing its evidence, Networks relied on 19 the legislated definition of "public interest", which 20 examines it in light of benefit to consumers in the 21 areas of pricing, availability, reliability, and quality 22 of electricity service. 23 Several intervenors have sought to address 24 issues which expand beyond these criteria. While 25 Networks maintains its position regarding the current 26 legislated definition, we have agreed to answer 27 questions during the hearing put to us by intervenors on 28 a without prejudice basis. We have, in fact, provided 17 Opening Statement (Aldred) 1 supplementary responses on these issues on that basis. 2 We have divided our evidence in this matter 3 into three panels. The first panel, which we will start 4 with this morning, will be the Quality Panel. They will 5 deal with the issues relating to need, proposed 6 facilities and alternatives to consider. 7 The second panel will deal with issues 8 relating to project economics and other public interest 9 considerations, and that is the panel where PHB Hagler 10 and Bailly will testify. 11 Finally, the third panel will handle matters 12 relating to project costs, construction and 13 administrative matters, and there will be a 14 representative from Hydro Quebec included on this 15 final panel. 16 In addition, on the final panel we have added 17 a witness to assist in answering questions arising out 18 of the EA process which was already undertaken in this 19 matter. 20 I have stated the project has been developed 21 with our partners at Hydro Quebec, and both Hydro Quebec 22 and Networks are ready to proceed with this project, 23 subject to approval. 24 Because of the engineering complexity of the 25 project, it has to be staged over a period of two years. 26 In order for Ontario consumers to realize benefits in 27 2003, the project must commence shortly. Therefore, at 28 the conclusion of this hearing, we may make some 18 Opening Statement (Aldred) 1 submissions as to the timing and nature of the decision 2 to be reflected. 3 I would like now to call my first panel of 4 witnesses. 5 THE PRESIDING MEMBER: Thank you, Ms Aldred. 6 --- Pause 7 SWORN: FRANK MACEDO 8 SWORN: CARMINE MARCELLO 9 EXAMINATION 10 MS ALDRED: Dr. Macedo, could you give us your 11 full name and indicate to us what your professional 12 affiliation is? 13 DR. MACEDO: I am Frank Macedo. I am Director 14 of Investment Planning at Hydro One Networks. I am 15 responsible for expenditures on our capital and OM&A 16 programs on all our assets. 17 MS ALDRED: Can you state your qualifications 18 and your experience, please? 19 DR. MACEDO: I have over 20 years experience 20 in planning and operations of transmission systems here 21 in Canada and in England. 22 Prior to my current position, I was Director 23 of Transmission Operations, also in Hydro One Networks, 24 responsible for real-time operations management of our 25 transmission assets. 26 Previous to that I held various positions in 27 planning and operations, again, in the CEGB in England 28 and here in Ontario Hydro. This included about three 19 HYDRO ONE PANEL 1, ex (Aldred) 1 years at the Clarkson System Control Centre, which is 2 now the IMO, where I was Manager of Integrated 3 Transmission Planning and Operations. 4 MS ALDRED: Could you tell us what your 5 academic background is, please? 6 DR. MACEDO: I have a degree in electrical bar 7 systems from London, England, and a Ph.D. in electrical 8 engineering from Bristol, England. 9 MS ALDRED: What memberships or professional 10 associations do you belong to? 11 DR. MACEDO: I am a licensed professional 12 engineer in the Province of Ontario. For the past two 13 years I have been the Vice-Chair of the North American 14 Electrical Reliability Council's Planning Standards 15 Subcommittee, responsible for developing reliability 16 standards across North America. 17 I have also been Chair of the Northeast Power 18 Coordinating Council's, NPCC's Working Group on review 19 of reliability standards. 20 For several years I have also been a member of 21 various NPCC task forces on planning and operations. 22 Finally, in relation to this project, I have 23 been Co-chair of various planning committees with our 24 interconnected utilities. 25 MS ALDRED: Have you given testimony before at 26 a Board hearing? 27 DR. MACEDO: Yes. In 1992 I was a senior 28 transmission planning witness in the Environmental 20 HYDRO ONE PANEL 1, ex (Aldred) 1 Assessment Board hearing on Ontario Hydro's Demand 2 Supply Plan. 3 MS ALDRED: Your more detailed CV has been 4 filed as part of the evidence. 5 DR. MACEDO: Yes, it has. 6 MS ALDRED: Could you please state for us the 7 area your evidence will cover this morning. 8 DR. MACEDO: My evidence will cover Exhibit B, 9 Tabs 1, 2 and 3, and I will be dealing with the need for 10 the project, the proposed facilities and policy matters 11 related to the project. 12 MS ALDRED: Can you confirm for us that that 13 evidence was prepared under your supervision and 14 direction and that the evidence is true to the best of 15 your present knowledge and belief? 16 DR. MACEDO: Yes. 17 MS ALDRED: Are there any changes to your 18 evidence? 19 DR. MACEDO: Yes, there are two changes. 20 The first one refers to the project cost 21 estimate. The Network Board has approved the project at 22 an estimated cost of $97.7 million subject to section 92 23 approval. Our current estimate is $96 million. Our 24 Panel 3 will provide further details. 25 The second correction is in response to OEB 26 Staff IR No. 7. We indicated that a 48-fibre optical 27 ground wire was to be used for telecommunication 28 purposes. This has now been revised to 24 fibres. 21 HYDRO ONE PANEL 1, ex (Aldred) 1 MS ALDRED: Other than those changes, do you 2 accept that material referenced as your evidence in this 3 case? 4 DR. MACEDO: Yes, I do. 5 MS ALDRED: Turning to you, then, 6 Mr. Marcello, could you please state your name for 7 the record and tell us what your professional 8 affiliation is? 9 MR. MARCELLO: My name is Carmine Marcello. I 10 am currently the Manager of Transmission and 11 Distribution Development in the Investment Planning 12 Division of Hydro One Networks. I have the geographic 13 responsibility for planning in the northern and eastern 14 part of the province. 15 MS ALDRED: Could you tell us what your 16 qualifications are, please? 17 MR. MARCELLO: I have worked in the electric 18 utility industry for 13 years. During that period I 19 have held numerous professional engineering positions in 20 the field of power system planning and operations. I 21 have a Bachelor of Applied Science Degree in Electrical 22 Engineering from the University of Toronto and a Masters 23 in Business Administration from York University. 24 MS ALDRED: Do you have other relevant 25 industry experience? 26 MR. MARCELLO: I am currently the Hydro One 27 Networks representative on the Northeast Power 28 Coordinating Council task force for the coordination of 22 HYDRO ONE PANEL 1, ex (Aldred) 1 planning. I have represented Hydro One Networks on the 2 OEB's industry task group that developed a transmission 3 system code. As part of that development effort, I 4 chaired the subcommittee dealing with system expansion. 5 MS ALDRED: And what areas will your evidence 6 cover today? 7 MR. MARCELLO: I will be covering Exhibits B, 8 Tabs 1, 2 and 3. The purpose of my direct evidence is 9 to describe the key elements of the project design and 10 the alternatives considered. 11 I will also be appearing on the third panel 12 where I will be dealing with the overall project 13 administration including the details of approvals. 14 MS ALDRED: Was this evidence prepared under 15 your supervision and is it true and correct to the best 16 of your knowledge today? 17 MR. MARCELLO: Yes, it is. 18 MS ALDRED: And are there any changes that you 19 want to make to that evidence? 20 MR. MARCELLO: None, other than the ones 21 Dr. Macedo has already referred to. 22 MS ALDRED: You therefore accept that evidence 23 as your evidence in this matter? 24 MR. MARCELLO: Yes, I do. 25 MS ALDRED: Dr. Macedo, will you please 26 provide the Board with an overview of the application? 27 DR. MACEDO: Hydro One is seeking approval for 28 leave to construct the proposed facilities under 23 HYDRO ONE PANEL 1, ex (Aldred) 1 section 92 of the OEB Act and the proposed facilities 2 are for a 1250 megawatt interconnection between Hydro 3 One's Hawthorne Transformer Station in Ottawa with Hydro 4 Quebec's substation at the Outaouais in Quebec. 5 The project has been developed and designed in 6 cooperation with Hydro Quebec. The project is required 7 to meet Networks transitional transmission licence and 8 it will provide benefits to Ontario consumers in three 9 specific areas: reduce energy prices, enhance 10 reliability and availability of supply. 11 MS ALDRED: Could you please elaborate on the 12 licence requirement you just referred to? 13 DR. MACEDO: The Ontario government, in its 14 November 1997 White Paper direction for change: 15 "Recognize the favourable impact of 16 energy prices if generators, both within 17 the province and outside, could 18 participate in a competitive market." 19 (As read) 20 Subsequently, in January 1999, the Market 21 Design Committee in its final report to the Minister 22 recommended that Networks, and I quote: 23 "Be expected to use best efforts to 24 expand intertie capacity with 25 neighbouring jurisdictions by 26 approximately 2,000 megawatts within 27 three years of market opening." (As read) 28 Now, in making this recommendation, the MDC 24 HYDRO ONE PANEL 1, ex (Aldred) 1 considered market power mitigation as an important 2 factor and that the interconnections would be a vehicle 3 to mitigate market par. The MDC recommendations 4 eventually became a requirement in Networks transitional 5 transmission licence approved by the Minister in April 6 1999. 7 MS ALDRED: Could you explain to the Board how 8 Networks approached the matter of energy cost savings? 9 DR. MACEDO: I should first start by saying 10 that the Networks is a transmission and distribution 11 company. It is not in a position to forecast how the 12 markets would operate and what benefits would arise from 13 competition in the marketplace. 14 Therefore for this project, Networks retained 15 a knowledgeable and recognized expert, PHB Hagler and 16 Bailly, who now calls himself PA Consulting, to carry 17 out this independent analysis. 18 PHB worked very closely with Networks to 19 ensure that they model the transmission systems in 20 detail and the systems surrounding the Ontario system 21 and this included interconnections right across eastern 22 Canada and the northeast seaboard. PHB performed 23 simulations based on a number of expectations for market 24 conditions in Ontario. 25 Now, PHB has estimated on a conservative basis 26 that Ontario electricity consumers are likely to save 27 around $240 million annually from lower electricity 28 prices related directly to this increase in transmission 25 HYDRO ONE PANEL 1, ex (Aldred) 1 capacity with Hydro Quebec. PHB estimates that, 2 dependent upon the market conditions, the savings could 3 range anywhere from $185 million to $295 million 4 annually. 5 Based on these expected savings, there will be 6 a short payback period for the $96 million capital 7 outlay to build the Ontario portion of the 8 interconnection. Therefore we believe that the project 9 is clearly economic for the Ontario consumers and PHB 10 will be here to discuss the study results in Panel 2. 11 MS ALDRED: Could you please explain the 12 nature of the reliability enhancement? 13 DR. MACEDO: The interconnection will, for the 14 first time, provide a permanent connection with Quebec 15 allowing us to import and export on a continuous basis. 16 This is not the case now. Today energy imports and 17 exports are achieved by disconnecting generation from 18 the Quebec system and connecting it to the Ontario 19 system and vice versa. 20 In doing so, the operating plant essentially 21 becomes part of the system to which it is connected. 22 Continuous access to new supply through a permanent 23 interconnection such as the one being proposed will 24 improve the overall adequacy, enhance reliability supply 25 to Ontario consumers. In addition, another 26 interconnection will improve the overall performance of 27 the electric power system in Ontario. 28 MS ALDRED: Could you tell the Board what you 26 HYDRO ONE PANEL 1, ex (Aldred) 1 mean when you say that there will be availability of new 2 supply? 3 DR. MACEDO: The interconnection makes 4 generation from the entire Quebec system and beyond 5 available to the Ontario market. And this is, as I said 6 earlier, this is in contrast to the current situation 7 where individual plants only in Quebec are connected to 8 the Ontario system. 9 The addition of this new interconnection will 10 therefore increase the level of access Ontario customers 11 will have to alternate sources of supply. 12 MS ALDRED: Can you describe for the Board the 13 current nature of existing interconnections with 14 neighbouring jurisdictions? 15 DR. MACEDO: We have been permanently 16 interconnected with our neighbours since the early 17 1950s. These interconnections have been used for three 18 main reasons. One is to enhance reliability of the 19 system. Second to provide emergency support, and the 20 third to permit economic energy transfers through 21 imports and exports. 22 The Ontario transmission system and the 23 interconnections are shown in the picture beside which I 24 am going to get my colleague to demonstrate. 25 You need to turn that a bit towards the Board, 26 Carmine. Thank you. 27 Now, the figure beside me you see is an 28 enlargement of Figure 1 of our prefiled evidence, 27 HYDRO ONE PANEL 1, ex (Aldred) 1 Exhibit B, Tab 3, Schedule 2. 2 The Ontario system is an integrated system 3 composed of 115 kilovolt, 230 kilovolt and 500 kilovolt 4 lines and the stations. The 500 kV system is a backbone 5 of the transmission system and it extends from Timmins 6 to Toronto, and from London to Ottawa. The rest of the 7 system, the 230 and 115 system, extends through most of 8 the province and, by and large, no one area is dependent 9 on the output of any one generating unit. That is 10 essentially what an integrated system is. 11 Now, Ontario is connected to New York at 12 Cornwall and Niagara areas; with Michigan in the Sarnia 13 and Windsor areas; with Manitoba in the Kenora area. 14 That is on the inset shown here in yellow, the Manitoba 15 and the Kenora area; and with Minnesota and the Fort 16 Frances area. 17 With Quebec there are several points of 18 connection along the Ottawa River. The first connection 19 was placed in service in the late 1920s but, as I stated 20 earlier, these are not permanent interconnections. 21 Utilization of these interconnections have 22 varied, depending on system conditions, market 23 conditions and transmission constraints, both within 24 Ontario and outside Ontario. Over the years, these 25 interconnections have played a very important role in 26 maintaining an economic and reliable supply -- I'm 27 sorry, economic and reliable electric boxes for Ontario. 28 MS ALDRED: Would you please describe what 28 HYDRO ONE PANEL 1, ex (Aldred) 1 work is currently under way to increase interconnection 2 capacity? 3 DR. MACEDO: There are two interconnection 4 projects currently under way which together will 5 increase our interconnection capacity by 650 megawatts. 6 These are the Maclaren and Michigan projects and I would 7 just like to describe the two of them. 8 The Maclaren project will upgrade an existing 9 115 kilovolt line with Maclaren Industries in Masson, 10 Quebec, with a new 230 kV interconnection. This will 11 provide 150 megawatt increase in capacity and is 12 scheduled to be in service in a few days. 13 Now, the Michigan project involves installing 14 base-angled regulating transformers, also known as phase 15 shifters, to control the path flow through the Ontario 16 system. These phase shifters will be installed or are 17 being installed on the Ontario-Michigan 18 interconnections. 19 The Michigan project will provide 20 500 megawatts capacity increase and this project is 21 expected to be in service in the second quarter of 2001. 22 With these projects, there would be a 23 remaining gap of 1,350 megawatts to meet Networks 24 license requirement. 25 MS ALDRED: What other option did you consider 26 for additional interconnection capacity? 27 DR. MACEDO: As part of our ongoing 28 relationships with our interconnected utilities, we 29 HYDRO ONE PANEL 1, ex (Aldred) 1 regularly review the performance of our 2 interconnections, the utilization of our 3 interconnections and, through that, jointly explore 4 opportunities to increase our interconnections. 5 We have been doing this for many years. In 6 fact, I personally have been doing this for the last 7 10 years. Because of this involvement, we are well 8 aware of the options that are available and the 9 characteristics of these options. So we assembled most 10 technically feasible options, particularly those that 11 have the significant increase in capacity, and rank them 12 according to unit cost in Ontario. These are summarized 13 in Exhibit B, Tab 3, Schedule 3. 14 They include capacity increases with Quebec 15 through this new high capacity interconnection with New 16 York by upgrading the Niagara area transmission. Now, 17 this is an internal constraint that has to be upgraded 18 in order to fully utilize the interconnections at New 19 York; with Michigan, by upgrading transmission west of 20 London and a new interconnection with Michigan; with 21 Pennsylvania through a new high capacity 22 interconnection; and with Manitoba through a new high 23 capacity interconnection. 24 Now, although we have ranked these options 25 according to unit cost in Ontario, unit cost itself is 26 not the soul criterion for selecting an option. Other 27 relevant considerations are a willing partner with 28 interconnections. A willing partner is extremely 30 HYDRO ONE PANEL 1, ex (Aldred) 1 important: favourable lead times, size of the capacity 2 increase, and the nature of the upgrade required. 3 Based on the comparison of options that I have 4 outlined, the Hydro Quebec alternative is by far the 5 best alternative. 6 Networks will continue to explore other 7 opportunities and other cost-effective options to 8 further increase our interconnections capacity. 9 MS ALDRED: Now, Mr. Marcello, can you tell us 10 what is required in order to build the interconnection 11 with Hydro Quebec? 12 MR. MARCELLO: New transmission lines are 13 needed to tie either new or existing transformer 14 stations in Ontario with those in Quebec. 15 It is at those transformer stations that the 16 power will be delivered and then transmitted to the rest 17 of the province via the transmission system that 18 Dr. Macedo described. It is also at the stations that 19 the voltages are converted or transformed to a lower 20 level to allow the power to be distributed locally. 21 In particular, tying Hydro Quebec and Hydro 22 One Networks together directly would cause some 23 problems. There are frequency and voltage problems that 24 could lead to outages and damaged equipment. 25 Dr. Macedo referred to this project as being 26 the first permanent interconnection. The way this is 27 going to be accomplished is through the use of high 28 voltage direct current converter equipment and it is 31 HYDRO ONE PANEL 1, ex (Aldred) 1 referred to as "HVDC" for short. 2 What this equipment does is take alternating 3 current, converts it into direct current and back into 4 alternating current. In doing so, the two systems can 5 now be tied together to allow continuous flow of power 6 in both directions. 7 MS ALDRED: What sorts of technical 8 considerations did you have to take into account in 9 developing this post-interconnection? 10 MR. MARCELLO: The development of the 11 transmission system as a whole, and this 12 interconnection, in particular, has been going on for 13 many years. When you look back at the types of factors 14 that are considered, they are numerous. A lot of these 15 factors are also the same sorts of items that the IMO is 16 looking at in their System Impact Assessment and that 17 NPCC looks at in their studies. 18 Specifically, we arranged a physical 19 connection in a manner that allows the facilities to be 20 operated in a safe and reliable manner. In adding any 21 new element to the system, and in this case the 22 interconnection, we have to look at what impacts there 23 are on the remaining system, specifically the electrical 24 capability of the remaining equipment, the short circuit 25 capability of that equipment and any changes that need 26 to be made have to be included and incorporated in the 27 design. 28 Reactive power requirements need to be 32 HYDRO ONE PANEL 1, ex (Aldred) 1 reviewed to ensure that the voltages on the systems are 2 maintained and, once again, any requirements have to be 3 factored into the design. 4 We also carry out transient and steady state 5 analyses. These are carried out to ensure that the 6 system will operate in a reliable manner. 7 A lot of these studies are used in the IMO 8 process and the NPCC and we ensure that we meet their 9 requirements in carrying out those studies. 10 MS ALDRED: Could you please describe your 11 detailed project design for which approval is being 12 sought? 13 MR. MARCELLO: This chart here behind 14 Dr. Macedo is a blow-up of Exhibit B, Tab 2, Schedule 3. 15 It is a subset of it, just so that we will be able to 16 view it a little better in this room, but I think we 17 have failed in that for the people in the back. 18 MS ALDRED: Could you put it on the other 19 easel there? 20 MR. MARCELLO: That is essentially what the 21 after would look like. 22 There is an existing right-of-way that runs 23 about 20 kilometres from Ottawa's Hawthorne TS, 24 transformer station, to the Ottawa River. On that 25 right-of-way today there are two sets of towers and each 26 tower carries a single circuit. What we are going to be 27 doing on this right-of-way is replacing each set of 28 towers with a new set and each set will now be capable 33 HYDRO ONE PANEL 1, ex (Aldred) 1 of carrying two circuits. So in total, once the project 2 is completed, there will be four circuits on two sets of 3 towers. The current two circuits that are there now 4 will be placed on one tower line and the other tower 5 line will carry the two new 230 kV circuits that will go 6 to Quebec to form the basis of this interconnection. 7 In replacing the towers, the new towers are 8 going to be located essentially in the same spot as the 9 existing tower thereby minimizing the environmental 10 impact. 11 That basically sums up the line portion of the 12 project. 13 The station work is largely at Hawthorne TS. 14 It is as this point where the lines will be tied to the 15 rest of the Ontario transmission system. The basic 16 facilities we will be providing there are additional 17 circuit breakers to accommodate the two new 18 interconnection circuits and to reconnect an existing 19 transformer. This connection arrangement will allow for 20 the safe and reliable operation and maintenance of the 21 facilities and the system. 22 Additional capacitor banks and their 23 associated circuit breakers will also be provided at 24 Hawthorne TS. These are necessary to maintain 25 acceptable voltage levels. 26 Within Hawthorne TS there are some breakers 27 that currently would not be capable of handling the 28 increased currents that will be going through the 34 HYDRO ONE PANEL 1, ex (Aldred) 1 station and those will be replaced with new higher rated 2 units. 3 Also protection and control facilities and 4 their associated telecommunications facilities will be 5 provided to ensure that the proper system operation 6 occurs under normal and abnormal conditions. 7 As a result of our short circuit analysis we 8 saw no need for any additional facilities with respect 9 to short circuit. 10 So overall, both facilities in Ontario will 11 provide the Ontario portion of the interconnection and 12 it will be good for 1250 megawatts of power flow. 13 MS ALDRED: Now could you briefly describe the 14 Hydro Quebec facility? 15 DR. MACEDO: Hydro Quebec's facilities will 16 run from that river crossing along 15 kilometres of 17 right-of-way to the Outaouais substation in Quebec. So 18 that is a total of 15 kilometres, two circuits, 230 kV 19 tower line. 20 At Outaouais the high voltage DC converter 21 equipment will be installed and these lines will be 22 terminated into that equipment and tied to the rest of 23 the Hydro Quebec system at that point. 24 MS ALDRED: Taking a step back then, 25 Dr. Macedo indicated that the preferred alternative was 26 an interconnection with Hydro Quebec. How was this 27 specific proposal developed? 28 MR. MARCELLO: We had to look at several 35 HYDRO ONE PANEL 1, ex (Aldred) 1 considerations to come up with this specific project 2 that is before the board today. In working with Hydro 3 Quebec we had to determine what the interconnection 4 location was going to be. Ottawa is where we are 5 proposing. There was a possibility of tying along 6 Cornwall into Quebec. We had to determine the 7 appropriate voltage level; 230 is what we selected. 8 There were 500 kV options as well. 9 Also, the location of the converter equipment 10 had to be determined. It is currently residing in 11 Outaouais. It could as easily have resided in 12 Hawthorne. Or half the equipment could have been 13 located on each, Hawthorne and Outaouais TS. Those 14 factors were all looked at. 15 In reviewing the overall costs and reliability 16 considerations it was decided that the preferred 17 alternative was an interconnection with two 230 kV 18 circuits between Hawthorne and Outaouais and the HVDC 19 equipment located at Outaouais TS. 20 That being established, the efforts now turned 21 to specifics of building two lines. How are we going to 22 physically route those lines and make those facilities 23 take place? 24 This was accomplished through a class 25 environmental process in accordance with the 26 requirements of the Minister of the Environment and the 27 Ontario Environmental Assessment Act. 28 Nine transmission line options were considered 36 HYDRO ONE PANEL 1, ex (Aldred) 1 under this process and after extensive public input an 2 alternative which balanced the environmental 3 considerations and costs was selected. The selection, 4 along with all the details of the assessment, were 5 documented in an environmental study report and the 6 Ministry of the Environment has accepted that study 7 report and no further environmental studies are 8 required. 9 MS ALDRED: Can you please summarize the key 10 aspects of your current facilities extension agreement 11 with Hydro Quebec? 12 MR. MARCELLO: Mr. Gagnon from TransEnergie 13 will be joining me on the third panel where we can 14 discuss this more fully. 15 The highlights are basically each party has 16 agreed to pay the cost of the facilities on their own 17 respective systems. Each party is obliged to obtain the 18 necessary approvals to get the project built. 19 The technical and construction details were 20 documented in the agreement and both parties are 21 committed to looking at options for improving on the 22 in-service date, which currently sits at December 2002 23 for the construction of the Ontario portion and an 24 overall project in-service of May 2003. 25 MS ALDRED: What is the current overall cost 26 of the project, including the Quebec portion? 27 MR. MARCELLO: As Dr. Macedo pointed out, our 28 portion is $96 million in Ontario. Hydro Quebec's 37 HYDRO ONE PANEL 1, ex (Aldred) 1 portion, it is my understanding that is $208 million; 2 $185 million is for station work at Outaouais TS and a 3 large component of that is the high voltage DC converter 4 equipment and an additional $.3 million for their line. 5 Once again, each party is responsible for 6 paying the full cost of the facilities on their 7 respective systems. 8 MS ALDRED: Can you tell us what the status is 9 of remaining technical approvals that are associated 10 with this project? 11 MR. MARCELLO: Once again, I will be 12 discussing this more fully on the third panel. 13 With respect to NPCC, the Northeast Power 14 Coordinating Council, we are expecting their approvals 15 in December. 16 A bit of background to NPCC's mandate: their 17 purpose is to promote the reliability and efficiency of 18 the electric service on the power system of its members 19 and NPCC's membership is made up of transmission 20 utilities, market operators and transmission customers 21 in eastern Canada, the northeast U.S., Quebec and 22 Ontario. Within Ontario, Hydro One, along with Ontario 23 Power Generation and the IMO, are members. 24 By implementing some basic criteria for the 25 design and operation of the interconnected power system, 26 NPCC strives to meet its goal of reliability and 27 efficiency. 28 Hydro One and Hydro Quebec have submitted 38 HYDRO ONE PANEL 1, ex (Aldred) 1 joint studies to NPCC's task force on system studies and 2 no major concerns have been raised. We expect final 3 approval early in December. 4 In terms of the IMO System Impact Assessment, 5 at the time of preparing for interrogatories I was 6 informed by the IMO that the studies would be completed 7 by the end of November. It is my understanding that 8 there are some possible delays but the assessment will 9 be delivered as soon as possible. 10 We at Hydro One have been working 11 cooperatively with the IMO in accordance with the market 12 rules and the connection assessment and approval process 13 in completing their System Impact Assessment. The scope 14 of their study will cover connection arrangement, 15 loadings, reactive power and short circuit assessments 16 and transient and steady state studies. 17 As I mentioned earlier, Hydro One has already 18 undertaken many of these analyses and incorporated the 19 outcomes in the current design that is before the Board. 20 Therefore, we do not anticipate any material 21 impact from the System Impact Assessment. 22 Once that assessment is completed, we plan to 23 respond with the study back to this Board. 24 MS ALDRED: Finally, then, Dr. Macedo, is 25 Networks committed to this project and ready to proceed? 26 DR. MACEDO: Yes, we are committed to the 27 project. We have obtained our Board of Directors 28 approval to proceed with the project, subject to a 39 HYDRO ONE PANEL 1, ex (Aldred) 1 favourable decision granted leave to construct. 2 We have an expectation that reasonable 3 expenditures will be eligible for recovery through 4 approved rates. Networks is ready and must move quickly 5 to achieve the benefits to Ontario electricity consumers 6 in 2003. 7 We have, either in hand or anticipate 8 receiving shortly, all approvals necessary to proceed 9 with the project. 10 Networks and Hydro Quebec are also committed 11 to reasonable efforts to achieve the earliest possible 12 in-service date so that Ontario consumers can achieve 13 their energy savings from the project and Hydro Quebec 14 the reliability benefits that the project provides. 15 MS ALDRED: That is the end of our direct 16 evidence. 17 THE PRESIDING MEMBER: Thank you, Ms Aldred. 18 Mr. Moran, please. 19 EXAMINATION 20 MR. MORAN: Thank you, Madam Chair. 21 Dr. Macedo, you have already referred to the 22 licence requirement that was imposed on Hydro One to 23 increase interconnection capacity. 24 This particular project is the one that you 25 have chosen to go with first. My question is this: Do 26 you anticipate proceeding with this project as acting as 27 a constraint on any other projects that you will have to 28 pursue to finish achieving the licence requirement? 40 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 DR. MACEDO: This project is clearly the best 2 alternative, having completed the first two that I 3 talked about, Maclaren and the Michigan project. 4 I cannot see why this would be a constraint to 5 proceeding with other projects. We would review the 6 other projects and make a decision based on the benefits 7 to Ontario consumers. 8 MR. MORAN: Do you anticipate any budgeting 9 constraints, given the commitment that this project 10 represents? 11 DR. MACEDO: It is our expectation that these 12 projects, if we bring them forward, we would bring them 13 forward because they have definite benefits to Ontario 14 consumers and therefore it is our expectation that we 15 will be able to recover the costs through future rates. 16 MR. MORAN: With respect to the use to which 17 this line can be put, I assume that you will agree that 18 power can go both ways and can be wheeled through 19 Ontario from Quebec to other jurisdictions. Right? 20 DR. MACEDO: That is correct. 21 MR. MORAN: You indicated that one of the 22 objectives was to enhance the commodity market, but you 23 were also careful to point out that your company is a 24 transmitter and is not directly involved in the 25 commodity market. 26 How does that fit in with Hydro One's 27 corporate objectives, this interest in enhancing the 28 commodity market? 41 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 DR. MACEDO: Networks supports the competitive 2 market and we will do whatever we can do to facilitate 3 the competitive market. That is all we can do. 4 The interconnections is one vehicle to 5 facilitate the competitive market. 6 MR. MORAN: How does that benefit your 7 shareholders? 8 DR. MACEDO: We would get a rate of return on 9 the investment that we make. 10 MR. MORAN: Now, the existing interconnection 11 capacity, you have indicated, is a total of 4,000 12 megawatts for all of the interconnections from Ontario 13 to other jurisdictions. Of that 4,000 megawatts, 1,265 14 megawatts is the current existing capacity between 15 Ontario and Quebec. Am I correct on that? 16 DR. MACEDO: Yes, that is correct. 17 MR. MORAN: Thank you. 18 I think you alluded briefly to the difference 19 between the existing connection and the proposed 20 connection. 21 As I understand it, and correct me if I am 22 wrong, the existing connection is not instantaneous and 23 you have to essentially disconnect certain things from 24 the circuit so that the power can be transmitted to 25 avoid stability problems that are experienced on the 26 Quebec side. Right? 27 DR. MACEDO: That is correct. 28 MR. MORAN: All right. What this project does 42 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 is it allows for a permanent connection. In other 2 words, instantaneous transmission is now possible for 3 the first time. Right? 4 DR. MACEDO: That's correct. 5 MR. MORAN: Okay. Now, as I understand it, 6 this will improve access to the market because you do 7 not have to go through the disconnects, it is 8 instantaneous, right, but you are converting an existing 9 connection. Is that right? 10 DR. MACEDO: There is an existing connection. 11 The comparison is -- I don't want you to compare the 12 two, because the one we have today is very -- it is 13 really for emergency support and the one we are talking 14 about is a permanent, high-capacity interconnection. 15 The two are not in the same league. 16 MR. MORAN: I understand. It is because of 17 this difference between being instantaneous and 18 non-instantaneous, right, primarily? 19 DR. MACEDO: Yes. 20 MR. MORAN: What is the existing capacity of 21 the existing interconnection which you have qualified as 22 being for emergency purposes? 23 MR. MARCELLO: Four hundred megawatts. 24 MR. MORAN: All right. So in effect, then, as 25 a result of this conversion, you are converting 26 400 existing megawatts to replace it with 1,250 27 megawatts of capacity. Is that fair? 28 MR. MARCELLO: You can characterize it in that 43 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 fashion, yes. 2 MR. MORAN: All right. 3 So for the purposes of the licence 4 requirement, are you going to count this as 1,250 or 5 1,250 minus 400? 6 DR. MACEDO: I will answer that. It is 1,250. 7 As I said, the existing interconnection is 8 really an emergency interconnection and it cannot be 9 used continuously to import and export. 10 The new interconnection allows us to do that, 11 and so we would regard the 1,250 as the contribution to 12 the licence requirement. 13 MR. MORAN: All right. In effect, you have 14 determined that the existing 400 really isn't enough 15 capacity and all of what you are doing is new capacity 16 regardless of the existing 400? 17 DR. MACEDO: That is correct. 18 MR. MORAN: Is that right? Okay. 19 One moment, please. 20 --- Pause 21 MR. MORAN: This proposed project is capable 22 of exporting power, as we have already indicated, from 23 or through Ontario to Quebec and importing power from 24 Quebec. What are you able to tell the Board about 25 identifiable or specific uses for the proposed project 26 for Ontario generators? 27 DR. MACEDO: Like any interconnection, this 28 one would allow generators in Ontario to access markets 44 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 outside of Ontario. 2 MR. MORAN: All right. Have you identified 3 who those might be at this point? 4 DR. MACEDO: We have not. Panel 2 may be able 5 to address that. 6 MR. MORAN: I have a similar question with 7 respect to Ontario loads. Would you leave that to 8 Panel 2? 9 DR. MACEDO: It depends on what your 10 question is. 11 MR. MORAN: Have you identified specific 12 Ontario loads that would take advantage of this proposed 13 project? 14 DR. MACEDO: Again, I would defer that to 15 Panel 2, yes. 16 MR. MORAN: Are you able to say anything about 17 the specific uses identified on the Quebec side for 18 Quebec generators or Quebec loads? 19 DR. MACEDO: Again, I can't answer that 20 question. Panel 2 will be best able to answer that. 21 MR. MORAN: All right. 22 Now, this project has a capacity of 1,250 23 megawatts. If it is under utilized, how are you going 24 to deal with that? 25 DR. MACEDO: The utilization is a function of 26 how the market is going to operate. As I said, we in 27 Networks would provide a facility and assets that would 28 facilitate the competitive market. How the 45 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 interconnection is used is really up to customers 2 supplies and not Hydro One Networks. 3 Panel 2 will discuss the economics of the 4 utilization, how that is going to impact prices and that 5 sort of thing. But what actually happens in reality, of 6 course, is a function of the marketplace. 7 MR. MORAN: The starting point, as I 8 understand it, for going with this project was primarily 9 to meet the licence requirement and in that context you 10 had to look at a number of options. I take it that you 11 didn't have to look at the do nothing alternative 12 because you can't meet your licence requirement with the 13 do nothing alternative. 14 Given that the do nothing alternative is a 15 tool to assess how good a proposal you have, one of the 16 tools that is used, what did you do to cover off the 17 fact that you didn't have to do that analysis this time? 18 DR. MACEDO: I believe the analysis has been 19 done. In arriving at the $240 million energy cost 20 savings to consumers in Ontario, that analysis was 21 carried out. In fact, the $240 million savings is the 22 difference between the cost to consumers without the 23 interconnection versus the cost with the 24 interconnection. 25 MR. MORAN: And it will be discussed by a 26 different panel? 27 DR. MACEDO: That's right. You will have the 28 experts on Panel 2 to discuss that. 46 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 MR. MORAN: Okay. 2 Could you describe the capital budgeting 3 process that you followed for this project? 4 DR. MACEDO: As I said earlier, the 5 expectation, based on the benefits to Ontario consumers, 6 it is our expectation that we will be able to recover 7 the capital expenditure through future aids. On that 8 basis we have allocated funds to proceed with this 9 project. 10 MR. MORAN: In that process perhaps you could 11 tell us how you actually addressed the four issues of 12 price and availability, reliability and quality of 13 service? How was that factored into that process? 14 DR. MACEDO: We are here before the panel to 15 seek approval for the project based on those very 16 factors: price, concerned investment of $240 million, 17 reduction in electricity prices to consumers, 18 reliability, interconnection links available, more 19 generation and therefore increases the overall adequacy 20 of generation to supply customer load in Ontario. So it 21 enhances reliability and, as I said, it also enhances 22 the performance of the system during emergency 23 conditions. 24 Availability of supply, it increases the level 25 of access to generators outside. And quality of supply, 26 there should be no change in quality of supply. 27 MR. MORAN: In the decision-making process, 28 what role did the price of transmission services play? 47 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 DR. MACEDO: We feel that, you know, the 2 $96 million expenditure in Ontario is more than 3 justified by the savings that I have talked about. 4 MR. MORAN: I am not sure that is an answer to 5 my question and I am just asking, the price of 6 transmission services, how did that play a role in the 7 decision-making process to go with this project? 8 DR. MACEDO: I think Panel 2 will talk about 9 the impact of this $97 or $96 million will have on the 10 tariffs that consumers will have to pay, and they could 11 tell you how they arrived at that. 12 In our analysis we looked at whether a 13 $96 million expenditure is an economically justifiable 14 expenditure and the answer to that is yes. 15 MR. MORAN: The last area I want to cover with 16 you involves you, Mr. Marcello. 17 You indicated or you referred to the IMO 18 System Impact Assessment that hasn't been delivered yet. 19 What is the current status of that? Have you entered 20 into an agreement with the IMO to prepare a System 21 Impact Assessment yet? 22 MR. MARCELLO: We have applied for a System 23 Impact and throughout the summer we have scoped out the 24 particulars of that and the final details have been sent 25 to the IMO. I have signed off on that agreement. I 26 have yet to received the signed back version. 27 MR. MORAN: Okay. So at this point there 28 isn't actually a completed agreement for the System 48 HYDRO ONE NETWORKS PANEL 1, ex (Moran) 1 Impact Assessment. Is that correct? 2 MR. MARCELLO: That is correct. 3 MR. MORAN: All right. Do you have any 4 indication from the IMO when they may execute their end 5 of it? 6 MR. MARCELLO: No, I don't. 7 MR. MORAN: In the course of your discussions 8 in establishing the scope for the SIA with IMO, have you 9 any indication of how long it will actually take to 10 carry out the System Impact Assessment? 11 MR. MARCELLO: I can't speak for the IMO's 12 plans. I can say that at the time of filing the 13 interrogatories I did check with the IMO in terms of the 14 November date which we supplied, and at the time it was 15 felt that that was appropriate. I understand that there 16 has been some slippage in that date and they are working 17 to have that study completed as soon as possible. 18 MR. MORAN: I note that the IMO is here today 19 so perhaps it is better for them to speak to this point 20 then. 21 Those will be all my questions, Madam Chair. 22 THE PRESIDING MEMBER: Thank you very much, 23 Mr. Moran. 24 The intervenor, Mr. Thompson, do you have any 25 questions? 26 MR. THOMPSON: Yes. 27 Thank you, Madam Chair. 28 EXAMINATION 49 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: Panel, I represent the City of 2 Cumberland in these proceedings and I have a few 3 questions. 4 First of all, Dr. Macedo, you have been with 5 Networks or its predecessor for 20 years I note. 6 DR. MACEDO: Since 1982. 7 MR. THOMPSON: Mr. Marcello, you have had 8 13 years experience? 9 MR. MARCELLO: That is correct. 10 MR. THOMPSON: So you would be familiar with 11 the approval processes that applied before the 12 section 92 came into force? 13 DR. MACEDO: That is correct. 14 MR. THOMPSON: When section 92 of the OEB Act 15 1998 came into force, the approval process for 16 constructing transmission facilities in Ontario changed. 17 Is that fair? 18 DR. MACEDO: If you are referring to 19 section 92 approval, yes. 20 MR. THOMPSON: Yes. And at that time the 21 Ontario Energy Board became what I call a final 22 approving authority? 23 DR. MACEDO: That is correct. 24 MR. THOMPSON: And is this the first case that 25 Networks has brought to the Board for such approval? 26 DR. MACEDO: That is correct. 27 MR. THOMPSON: Can you help me with the nature 28 of the approval process before section 92 came into 50 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 force? Could you briefly describe that, please? 2 DR. MACEDO: Depending upon the nature of the 3 project and whether it requires Environmental Assessment 4 Board approval or not, we would -- if it did require an 5 Environmental Assessment Board approval, we would go 6 through, do an environmental assessment and that 7 assessment, dependant upon the nature of the project, if 8 it was a small project, it would be done through the 9 Class EA, and for a bigger project a full environmental 10 assessment. 11 MR. THOMPSON: Okay. Well, assume I am 12 talking about a project that involves putting up new 13 towers and new lines on an existing right-of-way. Can 14 you just help me generally with the type of process for 15 getting approval of all aspects of that project? What 16 type of process applied before section 92 came into 17 force? 18 DR. MACEDO: There is the Class EA for minor 19 facilities, and of course, there is the full EA. I 20 think as a counsel has stated earlier, we will have a 21 witness on Panel 3 who actually carries out these 22 environmental assessments who would be able to describe 23 for you, in whatever detail you would like, the process 24 followed. I can answer it at a certain level but if you 25 are getting down -- 26 MR. THOMPSON: Yes. I am up to 40,000 -- 27 DR. MACEDO: Okay. 28 MR. THOMPSON: -- feet with you, doctor. 51 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 DR. MACEDO: Okay. 2 MR. THOMPSON: Excuse my voice. I have a 3 terrible cold. 4 But I take it from what you are telling me 5 that the only, if you will, public interest approval 6 process external to Hydro that applied was this 7 environmental-type process. Do I have that right? 8 DR. MACEDO: Yes, I would say so. 9 MR. THOMPSON: Okay. And then was it, in 10 effect, Hydro that determined whether all aspects of the 11 public interest were being served or not being served by 12 a particular project? 13 DR. MACEDO: No, it went through the 14 environmental assessment process or the Environmental 15 Assessment Board -- 16 MR. THOMPSON: Right. 17 DR. MACEDO: -- then the bigger public 18 interest would have been fully evaluated through that 19 process. 20 MR. THOMPSON: Well, the mandate of the 21 Environmental Board is limited to environment. Is that 22 correct? 23 DR. MACEDO: My understanding is that the 24 Environmental Assessment Board, through its process, 25 would examine the need for the project -- I am not 26 talking about the graph here, I am talking about the 27 full year -- the need for the project and the actual 28 facilities that would be used to satisfy the need, 52 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 including all the alternatives and make a determination 2 on whether that project should be approved or not. 3 MR. THOMPSON: Well, let me try it this way: 4 Had this application gone to the Environmental 5 Assessment Board, would you be here today? 6 DR. MACEDO: I expect so, yes. 7 MR. THOMPSON: For what, just to get a rubber 8 stamp of what the Environmental Assessment Board did or 9 for a broader assessment of the public interest? 10 DR. MACEDO: My understanding is that this 11 Board looks at the public interest as defined in the 12 legislation under section 92. 13 MR. THOMPSON: All right. Let me try it 14 this way: To the extent that factors other than the 15 environment were germane to a consideration of an 16 approval of a project before June of 2000, who made 17 those considerations? Would it be the Hydro Board of 18 Directors? 19 DR. MACEDO: I don't know where you are headed 20 with this, but could you repeat the question? 21 MR. THOMPSON: Well, I'm just trying to find 22 out who was the, if you will, custodian of the public 23 interest under the old process. Was it essentially 24 Hydro, Ontario Hydro? That is my understanding and 25 maybe I'm wrong. 26 DR. MACEDO: Well, certainly Hydro would take 27 into account all the factors associated with the 28 project, including cost to consumers, reliability and 53 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 where environmental issues were involved and required 2 Environmental Assessment Board approval we take it to 3 the Environmental Assessment Board. 4 So I don't know how else I can answer your 5 question. 6 MR. THOMPSON: No, I think you have 7 answered it. 8 The final approving authority, if you will, in 9 the old days, was Ontario Hydro. 10 DR. MACEDO: Subject to EAB approval. 11 MR. THOMPSON: And that has now changed with 12 the OEB Act? 13 DR. MACEDO: No, it is -- that is right. 14 MR. THOMPSON: Thanks. 15 Now, I don't know if you need to turn this up 16 but in -- this is a very high policy level question, but 17 in Exhibit No. 10.1, which is the City of Cumberland's 18 prefiled evidence, at Tab 3, we have there what I 19 understand to be information provided as handouts by 20 Ontario Hydro at open house meetings in Cumberland in 21 March of 1999. Would you take that subject to check? 22 DR. MACEDO: My colleague will answer these 23 questions. 24 MR. THOMPSON: Okay. 25 MR. MARCELLO: Tab 3, the series of panels, 26 the photocopies of -- 27 MR. THOMPSON: Yes. It is "Welcome! 28 Bienvenue! PUBLIC OPEN HOUSE". 54 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. MARCELLO: Right. 2 MR. THOMPSON: And then it has the 3 information. 4 MR. MARCELLO: Okay, yes. 5 MR. THOMPSON: And if you go to the fourth 6 page in, you will see a page entitled "OHSC - Hydro 7 Quebec Interconnection Existing and Proposed Tower 8 Options". Do you see that? 9 MR. MARCELLO: That is correct. 10 MR. THOMPSON: One of the options shown there, 11 down on the bottom, second from the right-hand side is a 12 steel pole option. Is that correct? 13 MR. MARCELLO: Yes. 14 MR. THOMPSON: The notes say that: 15 "All options can be used alone, twinned 16 and/or in combination with existing 17 structures". 18 Is that correct? That is what the notes say? 19 MR. MARCELLO: "All options can be used alone, 20 twinned and/or: 21 "...in combination... Actual heights may 22 vary... *spans will be shorter than 23 existing." 24 Yes. 25 MR. THOMPSON: Yes. So you could have steel 26 towers -- again -- 27 MR. MARCELLO: High. 28 MR. THOMPSON: You have a span of steel towers 55 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 then you could have a span of lattice towers. 2 MR. MARCELLO: Yes, that's possible. 3 MR. THOMPSON: So part of the -- part, if you 4 will, of the available options for a particular project 5 design. 6 MR. MARCELLO: Yes. 7 MR. THOMPSON: And how long has the steel 8 tower component of the array of options been available? 9 MR. MARCELLO: I couldn't give you an exact 10 date but many years. 11 MR. THOMPSON: Well, these towers that are 12 being replaced, the evidence, as I understand, indicates 13 that one line was built in 1932 and the second in 1949. 14 Has the steel tower option been available that long or 15 is it more recent? 16 MR. MARCELLO: The pole? 17 MR. THOMPSON: The pole, yes. 18 MR. MARCELLO: No. I wouldn't say it has been 19 available that long, no. More recent. 20 MR. THOMPSON: Okay. So big picture, what, 21 25-30 years? Is that the sort of -- help me with how 22 long they have been available. 23 MR. MARCELLO: Sure. I will -- 24 MR. THOMPSON: Is that sort of ballpark? 25 MR. MARCELLO: Ballpark. Close enough, yes. 26 MR. THOMPSON: Okay, great. Thanks. 27 Could you tell me, again at the very high 28 level, how frequently these steel towers are used in 56 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 Ontario -- poles, yes -- steel poles, right. 2 MR. MARCELLO: Generally we are proposing a 3 tower. It would be a lattice tower as a proposal and 4 steel poles would be looked on at a case-by-case basis. 5 MR. THOMPSON: All right, okay. 6 MR. MARCELLO: I wouldn't say that they are 7 located everywhere. 8 MR. THOMPSON: No, that is obvious, but they 9 are certainly located in many areas other than Kanata, 10 for example. 11 MR. MARCELLO: Yes. 12 MR. THOMPSON: And what I would like to have 13 you describe to us, if you could, is the considerations 14 at a policy level that go into a determination as to 15 when Hydro will install steel poles. Can you help us 16 with that? 17 MR. MARCELLO: Sure. 18 I think the thing to keep in mind is we have 19 to look at it on a case-by-case basis. Particular 20 circumstances you are dealing with, you would make a 21 determination whether the pole option was in fact a 22 viable one. We have put them in place on rights-of-way 23 where, because of limited width and the need to increase 24 the number of circuits or towers on the right-of-way in 25 a cross section, we required something more narrow. 26 That would be one scenario where it has been used. 27 In the case of Kanata, which you referred to 28 earlier, that was by order of the -- through the EA 57 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 process or the joint hearings. As a result of that, it 2 was determined that steel poles should be put in that 3 stretch through the Bridlewood community which was a 4 residential community, but at the same time the 5 remainder of that line which cuts through residential 6 areas in Nepean and Ottawa has lattice towers. 7 So I would say you really look at it 8 case-by-case. In this specific circumstance, on this 9 particular right-of-way we have here, we wanted to 10 minimize the environmental impact by staying with the 11 existing tower locations. So everywhere there was an 12 existing tower that we were taking down, we would 13 replace with a new one and the steel poles, because they 14 would require shorter span, didn't allow that to occur. 15 MR. THOMPSON: Okay. I plan to get into that 16 in more detail. 17 I think you are on the third panel, aren't 18 you, Mr. Marcello? 19 MR. MARCELLO: Yes, I am. 20 MR. THOMPSON: Okay. But I was more 21 interested in the high-level policy as to when these 22 poles have been used in the past, and you have given me 23 the limited width scenario which is the case where Hydro 24 One Network's predecessor put in steel poles. 25 MR. MARCELLO: And I have also given you a 26 scenario where we were -- 27 MR. THOMPSON: Yes, ordered to do so. 28 MR. MARCELLO: -- told to do so. 58 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: But is that all that motivates, 2 from a policy level, your decision? Let me come at it 3 this way. 4 Throughout Ontario, could you give me some 5 idea of the number of areas where these poles are used? 6 Is that something that can be done by undertaking and 7 brought forward for the third panel? 8 DR. MACEDO: We could do it, yes. 9 MR. THOMPSON: Could I have an undertaking 10 then, please? 11 MR. MORAN: That is Undertaking No. 15.1. How 12 would you like to describe that? 13 MR. THOMPSON: As I understand it, when 14 someone reappears at the third panel they are going to 15 describe generally the frequency and areas of steel pole 16 use in Ontario. Is that your understanding, doctor? 17 DR. MACEDO: Yes, that is correct. 18 MR. MORAN: So an undertaking to provide 19 information on steel pole use for Panel 3. 20 UNDERTAKING NO. 15.1: Dr. Macedo 21 undertakes to provide information on 22 steel pole use for Panel 3 23 MR. THOMPSON: Is, at a policy level, the fact 24 that a line is to run through an urban area one of the 25 considerations that is taken into account on 26 case-by-case analysis? 27 MR. MARCELLO: That would be a factor. 28 MR. THOMPSON: Is there a policy statement on 59 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 the use of steel poles within either Ontario Hydro or in 2 Hydro One? 3 DR. MACEDO: I am not aware of any. 4 MR. THOMPSON: Well would you check and when 5 you come back on the third panel, just confirm that 6 there isn't one and if there is one, produce it. Would 7 that be fair? 8 DR. MACEDO: Yes, that would be fair. 9 MR. THOMPSON: All right. So any other 10 factors that are considered at a policy level in 11 connection with the analysis of the steel pole option on 12 a case-by-case basis? We have got width of 13 right-of-way. We have got orders of tribunals. Passage 14 through urban areas is a factor. Are there any other 15 factors? 16 MR. MARCELLO: Cost is a factor. 17 MR. THOMPSON: Costs. Okay. 18 MR. MARCELLO: I think implicit in some of 19 that was environmental -- overall environmental 20 considerations. I think you are referring to it in 21 terms of urban but I would expand it to say 22 environmental as a whole. 23 MR. THOMPSON: All right. Anything else? 24 MR. MARCELLO: Offhand, no. 25 MR. THOMPSON: Turning then just briefly to 26 cost at a policy level, you were describing economic 27 feasibility, from the perspective of this Panel, as 28 being a situation that benefits of a project exceed its 60 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 cost. Did I understand that as your definition of 2 economic feasibility? 3 DR. MACEDO: That is right. 4 MR. THOMPSON: Hydro One says the benefits of 5 this project are what? 6 DR. MACEDO: I have said on a conservative 7 basis, it is $240 million a year. 8 MR. THOMPSON: That is, low side, 240? 9 DR. MACEDO: No, not low side. Low side was 10 $185 million. 11 MR. THOMPSON: All right. So low, 185. High 12 is what? 13 DR. MACEDO: It's 295. 14 MR. THOMPSON: So 295. And you say, on a 15 conservative basis, 240. And your estimated costs of 16 the project are $96 million. 17 DR. MACEDO: That is correct. 18 MR. THOMPSON: And somewhere in the evidence 19 with respect to the City of Cumberland there is an 20 estimate given that the steel pole option would add 21 $3 million to project costs and I think there was a high 22 of $10 million. Do those numbers ring a bell with you? 23 MR. MARCELLO: Yes, they do. 24 MR. THOMPSON: Okay. I can get into the 25 detail of how those were calculated, I assume, on 26 Panel 3. Is that right? 27 MR. MARCELLO: Just generally, at a high 28 level, in discussions with Cumberland various scenarios 61 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 were put forward and those estimates are basically a 2 unit cost which I think we can talk about in Panel 3, 3 and a length of area to cover and those lengths were 4 different scenarios we were talking about, short being 5 $3 million and relatively long being $10 million. 6 MR. THOMPSON: But even in the worst case 7 scenario, if it was 10 that would increase project costs 8 to 106 and a conservative estimate of benefits is 9 $240 million. So which steel poles -- based on your 10 definition of economic feasibility, the use of steel 11 poles would be economically feasible? 12 DR. MACEDO: Purely on economics, yes. But 13 the environmental assessment study that was carried out 14 tried to balance the two, environment and cost. As my 15 colleague has stated, a full environmental assessment -- 16 the process has been gone through and steel poles were 17 evaluated as part of that assessment. So you can focus 18 on economics, yes. It would be economic, but there 19 would be environmental impacts that my colleague has 20 referred to because you would not be able to replace 21 structure for structure. 22 MR. THOMPSON: I will get into that in more 23 detail on Panel 3. Because you mentioned economic 24 feasibility of benefits, I just wanted to nail down that 25 with this level of benefits, even if the costs were 26 10 per cent more, we would still have economic 27 feasibility being met based on your approach. 28 DR. MACEDO: Yes, that is correct. 62 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: Okay. I appreciate there are a 2 whole lot of other items that need to be considered in 3 the overall assessment. 4 The last question I wanted to ask you in 5 connection with this design issue is the economic life 6 of these poles. How long do they last? Are they 7 depreciated, over how many years? 8 MR. MARCELLO: I think Panel 2 can give you 9 the exact answer but my understanding is it is between 10 50 and 70. 11 MR. THOMPSON: $3 million amortized over 50 to 12 70 years is not a big number. Would you agree? 13 $10 million amortized over 50 to 70 years is not a big 14 number. In terms of again, rate impact, it is peanuts. 15 MR. MARCELLO: In terms of rate impact it is 16 small. In terms of environmental impact we will talk 17 about it in Panel 3 I guess. 18 MR. THOMPSON: Thanks. I notice on the 19 witness summary this Panel is claiming responsibility 20 for Ottawa-Carleton Interrogatories 1 and 2 which raised 21 this question of rights-of-way and compensation. Should 22 that be dealt with here or on Panel 3? 23 MS ALDRED: I think it would be more 24 appropriate for Panel 3. 25 MR. THOMPSON: Fine, I will leave it for 26 Panel 3. 27 Thanks very much, those are my questions. 28 THE PRESIDING MEMBER: Thank you, 63 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 Mr. Thompson. 2 Could I have a quick survey of the intervenors 3 and if they want to cross-examine this panel and how 4 long they think they will be? Mr. Klippenstein. 5 MR. KLIPPENSTEIN: Yes, Madam Chair, I would 6 like to and I would expect between 15 and 20 minutes of 7 questioning. 8 THE PRESIDING MEMBER: Mr. McArthur. 9 MR. McARTHUR: Madam Chair, yes, I would like 10 to ask some questions in probably five or ten minutes 11 although I am a little bit uncertain now in view of the 12 last question or the last response with reference to 13 Panel 3. 14 THE PRESIDING MEMBER: Okay, thank you. 15 Mr. Budd. 16 MR. BUDD: I have no questions, thank you. 17 THE PRESIDING MEMBER: Mr. Brown? 18 MR. BROWN: No questions, Madam Chair. 19 MR. GREENSPOON: Madam Chair -- 20 THE PRESIDING MEMBER: I'm sorry. 21 MR. GREENSPOON: -- Greenspoon. 22 THE PRESIDING MEMBER: Mr. Greenspoon. I 23 apologize. 24 MR. GREENSPOON: That is fine. No problem. I 25 would have some questions, about 10 or 15 minutes. 26 THE PRESIDING MEMBER: All right, I think then 27 that now might be a convenient time to break. We will 28 have a 15 minute break and return at about, according to 64 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 my watch, about 1140 a.m. 2 --- Upon recessing at 1123 3 --- Upon resuming at 1153 4 THE PRESIDING MEMBER: Please be seated. 5 Mr. Klippenstein, would you like to go next? 6 MR. KLIPPENSTEIN: Thank you. 7 I have thought a bit more about my questions 8 on the break and I may go a little bit longer than I 9 mentioned before. 10 THE PRESIDING MEMBER: The sooner you start, 11 the sooner you will finish! 12 --- Laughter 13 MR. KLIPPENSTEIN: My time projections come 14 with the usual limited warranty that accompanies lawyers 15 throughout the examination predictions. 16 THE PRESIDING MEMBER: Fair enough. 17 EXAMINATION 18 MR. KLIPPENSTEIN: I would like to ask a few 19 questions, I think specifically of Mr. Marcello in your 20 capacity as connected with the Northeast Power 21 Coordinating Council. 22 I understand from your testimony and from the 23 prefiled evidence that you sit on the Northeast Power 24 Coordinating Council as a representative of Hydro One. 25 MR. MARCELLO: On the Task Force for the 26 Coordination of Planning. That's that is correct. 27 MR. KLIPPENSTEIN: Okay. So the NPCC Task 28 Force on the Coordination and Planning is a subcommittee 65 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 or a body of the NPCC, and you represent Hydro One in 2 that committee. 3 MR. MARCELLO: Yes, that's correct. 4 MR. KLIPPENSTEIN: Okay. And the NPCC, as I 5 understand it, would include within its membership or 6 area, Ontario, Quebec, the northeastern United States. 7 Perhaps you could mention which northeast United States 8 are included the NPCC. 9 MR. MARCELLO: Largely, New York and New 10 England. I won't go through all the New England States. 11 MR. KLIPPENSTEIN: But it would be Maine, 12 Vermont, New Hampshire, those, plus others? 13 MR. MARCELLO: Basically, yes. 14 MR. KLIPPENSTEIN: Yes, okay. 15 And can I take it that as part of your general 16 work with Hydro One and your representation to the NPCC 17 Committee you would gain some general working knowledge 18 of the transmission lines in existence in northeastern 19 North America and of the flows through those 20 transmission lines in that region? Is that fair? 21 MR. MARCELLO: I have some knowledge in 22 that area. 23 MR. KLIPPENSTEIN: I would like to ask you 24 about how the proposed transmission line works, what the 25 theory is behind it, just to make sure I understand it. 26 As I understand it, Hydro Quebec's water 27 reservoir system essentially acts as a battery for 28 electricity power, if I can use an analogy, in the sense 66 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 that they can store water and thus store generating 2 capacity, and that battery analogy allows them to 3 time-shift power. 4 Is that a fair commonsense expression of what 5 Hydro Quebec can do? 6 MR. MARCELLO: I think, for the purposes of 7 what you are trying to explain, it probably makes sense, 8 yes. 9 MR. KLIPPENSTEIN: Those kinds of analogies 10 help us non-technicians to grapple with it, and if it is 11 misleading at any particular time feel free to tell me. 12 As I understand it, Hydro Quebec is by far the 13 largest operator of water reservoir systems in 14 hydroelectric systems in northeast North America. So it 15 would be the party with the largest time-shifting 16 capacity using reservoirs in northeast North America. 17 Is that fair? 18 MR. MARCELLO: I believe that that is a fair 19 comment, yes. 20 MR. KLIPPENSTEIN: And as I understand the 21 economics of the proposed transmission line -- I don't 22 want to get into it now, that is for the next panel I 23 understand -- but what makes this transmission line 24 economic is that it makes use of that time-shift 25 capacity, so that off-peak power in Ontario can be 26 purchased by Hydro Quebec, and then power to replace 27 that if you will, or time-shifted power can be sold back 28 to Ontario at peak hours. And it is that time-shifting 67 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 of power which is the driver behind the economics for 2 the transmission line. Is that fair? 3 MR. MARCELLO: I think that is the underlying 4 assumption of the PHB study. 5 Basically, Hydro Quebec sells into the Ontario 6 market, allows the price to be dampened in Ontario, in 7 which case $240 million of savings flow to the 8 electricity consumers, and in order to allow that to 9 occur they purchase off peak via this transmission line. 10 So I think that that is a fair assessment. 11 MR. KLIPPENSTEIN: Okay, thank you. 12 Just to link that to some Hydro Quebec 13 documents, the motion materials filed by Pollution Probe 14 include two documents from Hydro Quebec, one of its 15 divisions, and I would like to ask some questions about 16 those from your general knowledge, just to make sure I 17 understand them. 18 I have taken them out of the Motion Record, 19 for convenience, and I have mentioned this to your 20 counsel. I wonder, do you have the pages from the Hydro 21 Quebec Strategic Plan 2000-2004, called "Serving Our 22 Customers Better"? And, as well, the two pages from the 23 division of Hydro Quebec body, from the newsletter or 24 publication called "The Loop", of May 2000? 25 Do you have those two extracts? 26 MR. MARCELLO: Yes, I do. It looks like 27 pages 10, 11, 12, 13, and 14. 28 MR. KLIPPENSTEIN: Yes. 68 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 MR. MARCELLO: Okay. 2 MR. BUDD: Madam Chair, just before my friend 3 continues on this, I am just going to alert him, through 4 you, that if he is going to get into discussing what 5 Hydro Quebec's strategic plans are, I'm not sure how 6 helpful that is going to be to the Board in any event. 7 We have a witness on our third panel, and to 8 the extent that witness, who is from TransEnergie, a 9 Division of Hydro Quebec, could answer those questions, 10 then my proposal would be that we ought to have those 11 kinds of questions addressed to him rather than asking 12 Ontario witnesses to answer specific Quebec-type 13 questions. 14 THE PRESIDING MEMBER: Mr. Klippenstein. 15 MR. KLIPPENSTEIN: I'm not asking this witness 16 to speak for Hydro Quebec, obviously not. But the role 17 of Hydro Quebec and the possibilities of what Hydro 18 Quebec might do and its intentions are relevant to what 19 is going to happen with this transmission line. And 20 what I am referring to are these public, carefully 21 prepared presumably, statements by Hydro Quebec and 22 TransEnergie, and I propose to put them to the witness 23 to see whether he has any understanding of what they are 24 saying and to see whether he has any disagreements with 25 what they are saying. 26 And I will ask these again in the third panel, 27 but it would also make the order of the information 28 unworkable if this information was strictly limited to 69 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 words from the mouth of that witness who comes at 2 the end. 3 MR. BUDD: If I may, Madam Chair, the only 4 reply I have to that is that if he is asking these 5 witnesses for their understanding at least one of these 6 witnesses is going to be apparently appearing on the 7 third panel with Monsieur Gagnon, so I think those 8 questions could be put just as easily then. 9 THE PRESIDING MEMBER: Mr. Klippenstein and 10 Mr. Budd, to the extent that Hydro One Networks have 11 indicated that it is a joint project and that there was 12 a lot of joint planning, I think that Mr. Klippenstein 13 has the right to ask these panel members their 14 understanding of the nature of the public documents put 15 out by Hydro Quebec with the caveat that of course their 16 statements are not binding on Hydro Quebec and Hydro 17 Quebec will have the opportunity to respond in the third 18 panel. 19 Witnesses, if you don't know the answers and 20 would want to defer the answer to the third panel when 21 there is a Hydro Quebec witness available, then you are 22 welcome to do that. 23 Okay? 24 MR. KLIPPENSTEIN: Thank you, Madam Chair. 25 MR. MORAN: Madam Chair, should these 26 documents be marked as an exhibit? 27 MR. KLIPPENSTEIN: I was going to suggest 28 maybe two exhibit numbers, just for convenience of 70 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 reference. 2 MR. MORAN: Exhibit 14.3, excerpt from a Hydro 3 Quebec document, Strategic Plan 2000-2004. 4 Exhibit 14.3 an excerpt from a TransEnergie 5 newsletter, "The Loop". 6 THE PRESIDING MEMBER: Excuse me, 7 Mr. Klippenstein, as I understand it, that is Schedule A 8 to your motion, rather than Schedule B to your -- 9 MR. KLIPPENSTEIN: Schedule A and Schedule B. 10 I may have -- I was wondering if they were given 11 separate exhibit numbers or whether they together are 12 Exhibit No. 14.3, just for clarification. 13 MR. MORAN: You asked for separate, I gave 14 separate ones, 14.3 and 14.4. 15 MR. KLIPPENSTEIN: Thank you. 16 THE PRESIDING MEMBER: Excuse me, we decided 17 on two different exhibit numbers? 18 MR. MORAN: Mr. Klippenstein asked for two 19 separate numbers for the two excerpts. 20 THE PRESIDING MEMBER: So 14.3 and 14.4. 21 MR. MORAN: Yes. 22 THE PRESIDING MEMBER: Thank you. 23 EXHIBIT NO. 14.3: Document entitled 24 "Serving Our Customers Better" Strategic 25 Plan 2000-2004 26 EXHIBIT NO. 14.4: Document entitled 27 "The Loop" 28 MR. KLIPPENSTEIN: If I could ask you, 71 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 Mr. Marcello, to first turn to Exhibit 14.4, which is 2 excerpt from the publication called "The Loop", and turn 3 to the second page of that exhibit. And there is a 4 highlighted or marked sentence or two on the left-hand 5 column approximately in the middle. And I would like to 6 just ask you this: Do these statements accord with your 7 general understanding of the transmission line and power 8 usage on a regional basis? The publication says that, 9 beginning with, I believe it is the third sentence in 10 the third paragraph: 11 "Hydro-Qu‚bec has adjusted to these new 12 rules, which allow it to take advantage 13 of price fluctuations. When prices drop, 14 Hydro-Qu‚bec imports electricity to 15 distribute to its Quebec customers and 16 thus keep water in its reservoir. When 17 prices rise to about 30 times the average 18 price, as they did in July 1999 on the 19 New York and New England markets, 20 Hydro-Qu‚bec uses the stored water to 21 generate very profitable sales." 22 Now, first of all, does that generally accord 23 with your understanding of how the system works? 24 DR. MACEDO: May I take these questions? 25 MR. KLIPPENSTEIN: Sure. 26 DR. MACEDO: The principle outlined earlier on 27 in your cross-examination in fact is correct and that is 28 that the reservoirs are used for banking energy. From 72 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 the Ontario perspective, the important thing is to use 2 imports into Ontario to dampen the prices in Ontario. 3 Okay. And this is a mechanism that Hydro Quebec may use 4 to import into Ontario. The net effect on Ontario 5 customers is that the -- is that when the cost of 6 electricity is high, and that is at peak periods, that 7 is the time you want to import energy to dampen the 8 prices. 9 So the principles identified here are the 10 basis of the analysis. I don't want to comment on the 11 profitable sales and 30 times average price and that 12 sort of thing, but the principle, underlying principle, 13 is in fact valid. 14 MR. KLIPPENSTEIN: Okay. I wasn't 15 specifically focusing on the 30 times or the dates or 16 anything like that. 17 But just so I understand because this power 18 line has two ends to it, that first sentence, I just 19 want to make sure I understand that and if that is a 20 correct statement. 21 The first sentence or the second sentence that 22 I read says: 23 "When prices drop, Hydro-Qu‚bec imports 24 electricity to distribute to its Quebec 25 customers and thus keep water in its 26 reservoirs." 27 So Hydro Quebec can import power to save water 28 in its reservoirs and it is by that importing of outside 73 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 power that it is banking electricity. Is that right? 2 DR. MACEDO: That is correct. 3 MR. KLIPPENSTEIN: And that is part of the 4 picture at issue in here, because from Quebec's point of 5 view that is what it is going to do with this 6 transmission line. It is going to import power at 7 favourable prices, relatively favourable prices and bank 8 it. That is step one. Is that right? 9 DR. MACEDO: That is the basic principle, 10 right. And that is the principle that PHB used in their 11 analysis. 12 MR. KLIPPENSTEIN: Right. Okay. 13 Then continuing with the next sentence: 14 "When prices rise to about 30 times the 15 average price, as they did in July 1999 16 on the New York and New England markets, 17 Hydro-Qu‚bec uses the stored water to 18 generate very profitable sales." 19 So just looking at that as the other half of 20 the principle, at a level of principle, is that correct 21 in terms of the picture from Hydro Quebec's point of 22 view when a favourable price opportunity comes by, in 23 other words, they can sell power at a high price. They 24 can use that stored water to sell that power and make 25 money on the difference. Is that right? 26 DR. MACEDO: I cannot speak on behalf of Hydro 27 Quebec. What Hydro Quebec does and the motivation for 28 doing it you have to talk to the Hydro Quebec witness. 74 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 All I can tell you is from an Ontario 2 perspective that importing when the price is high in 3 Ontario will dampen prices of electricity in Ontario. 4 And that the mechanism for doing it through energy 5 banking sure, but the net effect is a reduction in 6 prices to consumers in Ontario. 7 What Hydro Quebec does or doesn't do and how 8 much profit they make or don't make is something you 9 should ask Hydro Quebec. 10 MR. KLIPPENSTEIN: Well, I'm not asking how 11 much profits Hydro Quebec makes. But let's be frank, I 12 mean this is not difficult economics and I would imagine 13 that Mr. Marcello has a pretty good idea of how these 14 power flows work and maybe I should ask Mr. Marcello. 15 But the principle in this statement seems to be buy low, 16 sell high, and Hydro Quebec can do that because it can 17 store electricity in the form of water. Is that right? 18 DR. MACEDO: That is right. I have said that 19 before. 20 MR. KLIPPENSTEIN: Okay. So in terms of the 21 second sentence, what Hydro Quebec is saying is absolute 22 common sense in that when it sees a favourable price 23 opportunity in another jurisdiction it can sell power, 24 which it didn't -- which it could buy at a previous time 25 at a cheaper price. Is that fair? 26 DR. MACEDO: That is fair. 27 MR. KLIPPENSTEIN: And in this particular 28 statement the example it uses is that it sells that 75 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 power to New York and to other New England States. Is 2 that right? 3 And this isn't a fanciful example, presumably 4 Hydro Quebec does do that. Right? 5 DR. MACEDO: Yes, they do it. 6 MR. KLIPPENSTEIN: All right. So what Hydro 7 Quebec then does sometimes is to import power from other 8 jurisdictions at a favourable price, use its water 9 reservoirs to store that power and then resell that 10 power to sometimes a northern United States jurisdiction 11 at a higher price to make a profit. Is that fair? 12 DR. MACEDO: Again, I -- 13 MR. KLIPPENSTEIN: This is not complicated. I 14 think it is quite simple. Am I not right? 15 DR. MACEDO: That is fine. I don't want to 16 speak on what Hydro Quebec does with regard to New 17 England and New York. I would like to talk about what 18 this interconnection will do for the customers of 19 Ontario and how Hydro Quebec is going to be able to 20 import and export into Ontario. 21 MR. KLIPPENSTEIN: Will you go this far with 22 me, that Hydro Quebec sometimes sells the imported 23 stored power to northeastern United States States? 24 DR. MACEDO: I cannot speak to that. 25 MR. KLIPPENSTEIN: Wait a minute. You mean 26 you don't know whether or not Hydro Quebec sometimes 27 sells imported stored power to northeastern United 28 States. Don't you know? 76 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 DR. MACEDO: No. I am saying that what Hydro 2 Quebec does with the energy it stores is something you 3 should ask Hydro Quebec. 4 MR. KLIPPENSTEIN: Well, I will but perhaps I 5 should ask Mr. Marcello. 6 Is it Hydro One's position that you don't know 7 whether or not Hydro Quebec sometimes sells cheap 8 imported power to the northeastern United States. Is 9 that something you don't know? You think it is -- I 10 mean it is -- I would think it very important for the 11 operations of Hydro One to know that and I am wondering 12 if you do know that? 13 DR. MACEDO: Hydro One is -- 14 MS ALDRED: I'm sorry. We are going to have 15 two witnesses, one on the second panel, Mr. Kline, who 16 can speak specifically to this issue. 17 And, secondly, I think Mr. Marcello -- 18 THE COURT REPORTER: Ms Aldred, you are not at 19 the microphone. 20 MS ALDRED: Oh, sorry. 21 I think Dr. Macedo and Mr. Marcello have both 22 answered that they would defer that type of questioning 23 about Hydro Quebec's behaviour to Hydro Quebec, and they 24 will be here on the third panel. 25 MR. KLIPPENSTEIN: Madam Chair, the reason I 26 ask these questions, as I said at the beginning, was 27 because Mr. Marcello is Hydro One's representative on 28 the NPCC, which is the regional coordinating planning 77 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 body for transmission and other related issues. That is 2 why I am asking Mr. Marcello and this panel that. 3 I just find it hard to believe that as part of 4 that overall planning function, in addition to their 5 ordinary business operations, they are -- I don't 6 understand why they are so reluctant to simply say what 7 I think is the obvious, what Hydro Quebec has said 8 publicly. If they don't know, they can say they don't 9 know. But it just seems to me we have a problem if they 10 are not willing to address that question. 11 It seems to me to be a legitimate question and 12 a very basic one. 13 THE PRESIDING MEMBER: Gentlemen, I think you 14 can speak to your general knowledge. 15 If it is your understanding that Hydro Quebec 16 sells to the northeastern United States, then perhaps 17 you can just simply state that and Mr. Klippenstein can 18 go on with his questions. 19 DR. MACEDO: Yes, thank you, Madam Chair. 20 I did say that Hydro Quebec does sell to New 21 York. There is no question about it, New York and New 22 England. 23 I just wanted to mention that Hydro One is a 24 transmission and distribution network. I cannot sort of 25 emphasize that more. We facilitate imports and exports. 26 You are asking us as Hydro One witnesses here to talk 27 about how the markets are going to operate and for that, 28 we have retained PHB, and PHB on Panel 2 will be able to 78 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 address how the markets, not only in Ontario and Quebec, 2 but also in the surrounding jurisdictions, would impact 3 this interconnection. So all of these questions really 4 should be addressed to Panel 2. 5 But I am stating that yes, I do know that 6 Hydro Quebec sells energy to New England and New York. 7 MR. KLIPPENSTEIN: Let me just ask you again 8 the approximate question I was trying to get answered 9 before. I thought it was obvious. 10 It is accurate and true, isn't it, that as 11 part of its operations, and it is common knowledge I 12 would have thought, particularly to the planning 13 council, that Hydro Quebec sometimes imports cheaper 14 power, stores it, and sells some of that cheaper 15 imported power to the northeastern United States. Can 16 you agree with that? 17 DR. MACEDO: Not from Ontario. 18 MR. KLIPPENSTEIN: That wasn't my question. 19 That wasn't my question. 20 DR. MACEDO: No, no, but that is the 21 implication of the question. 22 MR. KLIPPENSTEIN: Well, answer my question 23 first. 24 DR. MACEDO: Okay. My thing is that I know 25 that energy is exchanged between Ontario and Quebec at 26 off-peak times and returned at peak times. That is done 27 today. 28 What transpires between New York, New England 79 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 and Hydro Quebec, I am not aware of, other than that 2 Hydro Quebec sells energy to New York and New England. 3 MR. KLIPPENSTEIN: Just so I understand, my 4 question was: does Hydro Quebec sell cheap imported 5 power that it stores by means of its reservoir at a 6 higher price to the northeastern United States? Are 7 you -- 8 THE PRESIDING MEMBER: Excuse me, 9 Mr. Klippenstein. 10 I think that the witnesses have said that that 11 will be dealt with in Panel 2 and I think that that was 12 their answer to your question. 13 As I understand it, this Panel are answering 14 high-level policy questions with respect to the project 15 issues such as the economics are going to be dealt with 16 with another panel. 17 MR. KLIPPENSTEIN: All right. 18 Mr. Marcello, as the Hydro One representative 19 to the Regional Planning Committee, can you advise me, 20 with the completion of the proposed transmission line, 21 will it be possible for Hydro Quebec to purchase power 22 from Ontario and resell that power to the northeastern 23 United States? 24 MR. MARCELLO: In terms of purchasing from 25 Ontario, yes, they can. And can they physically resell 26 to the U.S.? Yes, they can. 27 MR. KLIPPENSTEIN: Okay. So just so I 28 understand that, it is anticipated that when a 80 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 transmission line is completed, it will be physically 2 possible for Hydro Quebec to purchase power from 3 Ontario, store it through the reservoir mechanism and 4 resell that power to the northeastern United States. It 5 will be physically possible. It will be doable. Is 6 that fair? 7 MR. MARCELLO: You said "anticipate" so I 8 would say I don't have any anticipation. 9 MR. KLIPPENSTEIN: My question was whether it 10 was physically doable. 11 MR. MARCELLO: Physically the facilities can 12 be used to buy and sell 1,250 megawatts. So Hydro 13 Quebec can buy 1,250 and can sell 1,250 on our 14 interconnection. They also have other interconnections, 15 as you have pointed out, and I don't have the specific 16 capability of those. 17 MR. KLIPPENSTEIN: I am not asking for 18 specific capabilities. I am asking as you are the Hydro 19 One representative to the regional planning body, just 20 for clarification, Hydro Quebec could use the new 21 transmission line to buy Ontario power and then Hydro 22 Quebec can sell that power to the northeastern United 23 States. That is physically possible. Is that correct? 24 I think that -- 25 MR. MARCELLO: I believe I have already 26 answered that. Yes, I think that is physically 27 possible. I think it is physically possible for Hydro 28 Quebec to buy from New York and sell into Ontario. I 81 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 think it is physically possible once the facilities are 2 there that they can be used in numerous circumstances 3 that will only be limited, I think, by the market and it 4 goes back to the point we are providing a facility that 5 will help facilitate the market. 6 DR. MACEDO: Mr. Klippenstein, may I just 7 clarify a point, and that is that NPCC is a reliability 8 organization. Their prime purpose is to promote the 9 reliability of transmission systems in northeastern 10 North America. The NPCC does not deal with commercial 11 matters. Buy/sell is not an item discussed within NPCC. 12 Those are left to individual utilities, parties to 13 negotiate outside of NPCC. What NPCC is concerned with 14 is that having made those arrangements that the system 15 is operated in a reliable and secure manner. 16 MR. KLIPPENSTEIN: Again, Mr. Marcello, as 17 part of your role in the NPCC planning committee or task 18 force, could I refer you to Exhibit No. 14.4 -- I'm 19 sorry, I believe it is 14.3, page 36, bottom left of 20 page 36. 21 MR. MARCELLO: Okay. 22 MR. KLIPPENSTEIN: And that part of Hydro 23 Quebec's strategic plan talks about the expiry of 24 long-term export contracts by 2002. Presumably as part 25 of your overall planning knowledge of the northeastern 26 North American region, you would be aware of whether or 27 not Hydro Quebec does have some long-term export 28 contracts that are expiring around 2002. Can you 82 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 confirm that Hydro Quebec has such contracts? 2 MR. MARCELLO: Actually, I cannot confirm 3 that, no. 4 MR. KLIPPENSTEIN: Are you aware of whether or 5 not Hydro Quebec has some long-term export contracts 6 that are expiring in the near future? 7 MR. MARCELLO: Other than the fact that you 8 have provided me this paper, I have no personal 9 knowledge of that, no. 10 MR. KLIPPENSTEIN: So you wouldn't know either 11 that this is true of your own knowledge or that it is in 12 some way not accurate. You wouldn't know either way 13 then? 14 MR. MARCELLO: No, I couldn't comment on that. 15 MR. KLIPPENSTEIN: Okay. Can you tell me as 16 someone who is charged with coordinating planning for 17 the northeastern representative, in part -- of the 18 northeastern region, in part, assume for the moment that 19 Hydro Quebec's strategic planning document is true and 20 that Hydro Quebec does have some export contracts 21 expiring around 2002. 22 Would it be fair to say that one implication 23 of that is that some transmission capacity that had been 24 previously tied up by long term contracts would be 25 freed up? 26 MS ALDRED: I would just like to clarify. I 27 don't think Mr. Marcello ever told anyone he was charged 28 with planning with the NPCC and I think it might be 83 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 helpful if he were to explain to us what his role is 2 there just so that Mr. Klippenstein can focus his 3 questions. 4 MR. KLIPPENSTEIN: That would be helpful, 5 thank you. 6 THE PRESIDING MEMBER: Mr. Marcello. 7 MR. MARCELLO: The task force on the 8 coordination of planning has the primary responsibility 9 for overseeing a document which is referred to as A2, 10 basic criteria for the planning and operation of the 11 interconnected system. Basically what this document 12 lays out are the rules by which the system should be 13 designed and operated and I think Dr. Macedo pointed out 14 the real focus of NPCC is keep the lights on. 15 After 1965 there was a big blackout. The need 16 for a coordinating council was established. NPCC was 17 formed. There are other coordinating councils and they, 18 under an umbrella which is referred to as the North 19 American Electric Reliability Council, has a mandate to 20 make sure that, in simple terms, the lights stay on. 21 So in doing that, from a transmission 22 perspective, which is where I am coming from and my role 23 on NPCC, and I think you have to separate my role on 24 NPCC from that of maybe a former Ontario Hydro 25 representative who would have looked at generation, 26 transmission and system security all perhaps in one or 27 two people. I am there from a transmission perspective. 28 I can comment that the lines we are putting in 84 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 here meet their basic criteria. I can say with 2 certainty that we looked at all the recognized criteria 3 and contingencies that are specified in that document. 4 We have done analysis and in doing that, the facilities 5 we are putting forward will meet those basic criteria; 6 the lights will stay on. That is the role I have in 7 NPCC -- sorry -- as Hydro One's representative on that 8 committee. 9 The committee does discuss proposals from 10 Hydro One, from TransEnergie or any other jurisdiction 11 and we review those proposals again, against these 12 criteria. There is a task force of system studies which 13 physically carry out these studies and applies them 14 against the criteria for which we are basically mandated 15 to ensure that it is kept current and reflects the 16 reality of ensuring the reliability is maintained. 17 THE PRESIDING MEMBER: Thank you, 18 Mr. Marcello. Does that help you focus your questions, 19 Mr. Klippenstein? 20 MR. KLIPPENSTEIN: Yes, I think it does. 21 Thank you, Madam Chair. 22 Now, Mr. Marcello, or Dr. Macedo, you have 23 agreed that it will be physically possible for Hydro 24 Quebec to use the proposed transmission line to purchase 25 Ontario power and resell it to the northeastern United 26 States. 27 Now, let me ask about the assumption about 28 power coming back to Ontario. I think you mentioned, 85 HYDRO ONE NETWORKS PANEL 1, ex (Klippenstein) 1 Dr. Macedo, that one of the prime benefits economically 2 of the proposed transmission line is that the incoming 3 power from Hydro Quebec will dampen prices in Ontario at 4 peak periods. Is that right? 5 DR. MACEDO: That is correct. 6 MR. KLIPPENSTEIN: All right. Do you make 7 any assumption -- I guess it is inherent -- you do make 8 an assumption that Hydro Quebec will sell power back to 9 Ontario, or power to Ontario, using a new transmission 10 line during peak periods? Is that fair? 11 DR. MACEDO: Again, you are getting into the 12 area that Panel 2 will discuss. They have made various 13 assumptions in the analysis and they will be able to 14 defend those assumptions and so, if I may, I would like 15 to defer questions like that to Panel 2. 16 --- Pause 17 MR. KLIPPENSTEIN: I think, Madam Chair, those 18 are all my questions for this panel and I will direct 19 the others to the next panel. 20 THE PRESIDING MEMBER: Thank you, 21 Mr. Klippenstein. 22 Mr. McArthur. 23 EXAMINATION 24 MR. McARTHUR: Thank you, Madam Chair. 25 Yes, I do have some questions based on the 26 fact first that the witness summary, Panel 1, this 27 panel, refers to Ottawa-Carleton's Interrogatories so I 28 would like to put some questions to this particular 86 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 panel, if I may. Of course, if they wish to defer to a 2 later panel I am sure they will. 3 The second reason I would like to ask some 4 questions now, Madam Chair, is that I had committed to 5 two days of hearings starting yesterday and I am 6 unavailable tomorrow, unfortunately, because of another 7 commitment. So with your leave, Madam Chair, I have a 8 few questions for just a few minutes. 9 To the panel, Mr. Marcello I think, it is 10 pretty obvious from what we have heard this morning that 11 pricing is an issue squarely before the Board. Is that 12 correct? 13 MR. MARCELLO: Yes, that is correct. 14 MR. McARTHUR: Whatever the definition of 15 public interest, pricing is certainly one of them. 16 MR. MARCELLO: Yes. 17 MR. McARTHUR: Is it fair to say, 18 Mr. Marcello, that additional costs translate to higher 19 transmission rates which must be borne by all consumers? 20 Is that a fair statement? 21 MR. MARCELLO: I think that is a fair 22 statement, yes. 23 MR. McARTHUR: It is one, in fact, that comes 24 from Hydro One's evidence. 25 Mr. Marcello, following on from that, might 26 additional costs include land costs? 27 MR. MARCELLO: Yes, they would. 28 MR. McARTHUR: Hydro One has filed evidence 87 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 and in its answer to interrogatories it has taken the 2 position that existing easements are adequate. Is that 3 correct? 4 MR. MARCELLO: Yes, that is correct. 5 MR. McARTHUR: And we are talking about 6 Ottawa-Carleton's easements and easements belonging to 7 other land owners? Is that correct? 8 MR. MARCELLO: Yes, sir. 9 MR. McARTHUR: Hydro One has filed a sample 10 easement with its interrogatories. Is that correct? 11 MR. MARCELLO: Yes, we have. 12 MR. McARTHUR: Is it also correct that that is 13 a 1990 document? 14 MR. MARCELLO: I would have to check it but if 15 you say it is, then it is. Can you just refer -- 16 MR. McARTHUR: Yes, I can refer you to it if 17 you wish. It is OEB Staff Interrogatory No. 65, Tab 1 18 in Hydro's evidence, Hydro One's evidence on 19 interrogatories, at least Hydro's answer to 20 interrogatories. 21 MR. MARCELLO: Sorry, I was looking under your 22 interrogatories. That is why I couldn't -- 23 MR. McARTHUR: Okay. No, this is an answer to 24 staff's interrogatories. 25 MR. MARCELLO: Okay. 26 MR. McARTHUR: Would you say that that 27 particular easement is typical of the easements with 28 respect to this particular line, proposed line? 88 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 MS ALDRED: I'm sorry, I do not seem to have 2 an easement attached to 65. 3 MR. MARCELLO: To 64? 4 MR. McARTHUR: Do you have it? 5 MR. MARCELLO: Page 64? Because I don't have 6 one under page 65. 7 MR. McARTHUR: Okay. I will find it. 8 --- Pause 9 MR. McARTHUR: It's 61, Madam Chair. OEB 10 Staff Interrogator No. 61. 11 THE PRESIDING MEMBER: Yes, thank you. It 12 is 61. 13 MR. MARCELLO: Thank you. 14 MR. McARTHUR: The attachment to the response 15 is a sample easement. 16 MR. MARCELLO: I'm sorry. The question again? 17 MR. McARTHUR: Would you say that is a typical 18 Hydro One easement for these lands? 19 MR. MARCELLO: Yes. 20 MR. McARTHUR: Have you looked at them all? 21 MR. MARCELLO: No, I haven't. 22 MR. McARTHUR: Do you know how many there are? 23 MR. MARCELLO: No, I don't. 24 MR. McARTHUR: Do you know how old some of 25 these easements are? Is it fair to say that some of 26 them are 50 or 60 years old? 27 MR. MARCELLO: Given that the right-of-way was 28 built or established in the thirties I wouldn't be 89 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 surprised to hear that some are that old. But I have 2 no -- real estate isn't my area. I have no way to 3 confirm or deny that. 4 MR. McARTHUR: All right. From what you have 5 just said then some of them could be 70 years old? 6 MR. MARCELLO: Perhaps. 7 MR. McARTHUR: Has Hydro One discussed with 8 Ottawa-Carleton or any of the affected land owners these 9 particular easements and the uses described therein? 10 MR. MARCELLO: Not to my knowledge. 11 MR. McARTHUR: Based on the evidence 12 submitted, prefiled by Hydro One that the easements are 13 sufficient, I take it then that Hydro One has made a 14 unilateral determination that these easements are 15 adequate. 16 MS ALDRED: I am wondering if you are getting 17 into legal questions which I would be prepared to deal 18 with in argument. I don't want to stop my friend, but 19 Mr. Marcello isn't a lawyer and to a large extent, the 20 adequacy or sufficiency of easements, it seems to me, is 21 a legal question. 22 MR. McARTHUR: Well, I am not sure, Madam 23 Chair, whether that is a legal question. All I am 24 asking is has there been consultation with the 25 landowners in question. The answer has been no. It 26 follows therefore, that there has been a unilateral 27 determination, I believe, and I am just asking for 28 confirmation of that. There doesn't seem to be too much 90 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 legal about that. 2 MR. MARCELLO: Basically, Hydro One had the 3 documents reviewed by legal counsel, and they gave us 4 the opinion that these were sufficient for what we were 5 planning to do on this right-of-way. 6 MR. McARTHUR: All right, thank you. 7 If, however, that position is incorrect, or 8 the legal advice was incorrect, which I am not saying it 9 was, but if it was, then there may be an extra cost 10 involved. Isn't that correct? For land cost. 11 MR. MARCELLO: We are speculating now, but, 12 obviously, if there are additional costs, then the costs 13 of the project will go up. 14 MR. McARTHUR: All right. To speculate a 15 little bit more then, or perhaps not, on the evidence 16 you have already given, that will be borne by the 17 consumer, if there is an extra cost? 18 MR. MARCELLO: Once the project is complete, 19 all costs will be brought back to the OEB for inclusion 20 into the rate base and we would expect to give a full 21 accounting of what happened to increase any cost. 22 MR. McARTHUR: Okay, thank you. 23 I would just like to ask you a couple of 24 questions, or perhaps you can clarify for me the exact 25 nature of the construction changes, or the changes in 26 construction. 27 You said in your evidence that all towers will 28 be replaced with new. Can you clarify that just a 91 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 little for me. What do you mean exactly? They will be 2 built in the same spot, will they? 3 MR. MARCELLO: The towers, where they are 4 situated on the right-of-way today -- 5 MR. McARTHUR: Yes. 6 MR. MARCELLO: -- will be removed and new 7 towers will be put in place on the same spot. 8 MR. McARTHUR: Why exactly do you need new 9 towers? 10 MR. MARCELLO: In order to -- we have the 11 existing right-of-way -- 12 MR. McARTHUR: Yes. 13 MR. MARCELLO: -- and currently there are two 14 circuits on that right-of-way and these circuits largely 15 supply area load. The township -- or the City of 16 Cumberland and various other areas are supplied from 17 those existing circuits. So it is not a matter of we 18 will just get rid of them and build two new circuits to 19 Hydro Quebec. We still need those circuits. 20 So when you look at the right-of-way and the 21 real estate that is there, we have two circuits on them. 22 When you look at what is required when we are done, we 23 are going to need four circuits: two for Hydro Quebec 24 interconnection and two to continue the existing supply. 25 There are currently two rows of towers with 26 one circuit on each. So what we are proposing is 27 replace the existing tower with one that is capable of 28 holding two circuits so at the end we will have four 92 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 circuits on the right-of-way. Two to ensure that the 2 continuing supply of power is maintained, and two new 3 ones to tie to Hydro Quebec. 4 MR. McARTHUR: As a non-engineer, you will 5 have to explain that to me a little more. 6 MR. MARCELLO: Okay. 7 MR. McARTHUR: Is this because the circuits 8 are heavier? I mean are they bulkier or heavier or what 9 is the reason? 10 MR. MARCELLO: What is the reason for newer 11 circuits? 12 MR. McARTHUR: Well, you are going to replace 13 two circuits with four -- 14 MR. MARCELLO: Okay. 15 MR. McARTHUR: -- and you are going to require 16 new towers. 17 MR. MARCELLO: Okay. 18 MR. McARTHUR: Is this because the circuits 19 take up more space, or because they are heavier or -- 20 why can you not put four circuits on two towers? 21 MR. MARCELLO: Okay. Why can't they put four 22 circuits on two towers? 23 MR. McARTHUR: The two towers that are there 24 now. 25 MR. MARCELLO: Oh, the existing towers are not 26 designed to accommodate four. They don't have the 27 clearances necessary. They don't have the physical, 28 mechanical strength associated with carrying additional 93 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 loads. 2 The physical foundations that are supporting 3 it aren't sufficient to carry those additional 4 mechanical -- and all those physical stresses aren't 5 sufficient with what is there now. 6 MR. McARTHUR: How then do the new towers 7 correct those things that you just explained to me, such 8 as clearances, foundations -- not the physical strength? 9 How do the new towers correct that situation? 10 MR. MARCELLO: The new towers are basically 11 designed to be able to support the new circuits and the 12 new forces. So -- I am not a mechanical engineer, but 13 the thickness of the metal is greater; greater 14 clearances are accommodated by having taller towers. 15 Those sorts of aspects are brought to bear. 16 MR. McARTHUR: Okay. Is it fair to say there 17 is quite a change then in the nature of these towers? 18 MR. MARCELLO: The towers are different. In 19 terms of the real estate, though, they are staying on 20 the same footprint, the same location -- 21 MR. McARTHUR: Yes, I understand that. 22 MR. MARCELLO: -- along the right-of-way. 23 MR. McARTHUR: Mr. Marcello, if we might just 24 go into a little different area for a moment. 25 Hydro One obviously has a policy with respect 26 to reconstructions on existing easements, does it not? 27 MR. MARCELLO: I personally don't know; that 28 is not my area of expertise. 94 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 MR. McARTHUR: All right. Can you say whether 2 in the past it has had a policy? 3 MR. MARCELLO: I'm sorry. Maybe I am not 4 understanding the question. Could you repeat it? 5 MR. McARTHUR: If Hydro One is required to 6 rebuild its towers on an existing easement, does it have 7 a policy -- or I am actually asking -- did it have a 8 policy with respect to the landowners? 9 MR. MARCELLO: I would think in reviewing our 10 easement documents if they were not sufficient we would 11 be coming back to the landowner to negotiate a new 12 easement. 13 One of the things to keep in mind, and it goes 14 back to a discussion we will probably be getting into on 15 the third panel, is why not steel poles? Steel poles 16 would require -- we would not be able to stay on the 17 existing footprint. We would require more poles. And 18 in those circumstances, if that was in fact a necessary 19 outcome, if that was the outcome at the end of the 20 environmental assessment, we would be coming back to 21 Ottawa-Carleton saying, "We need additional easement 22 requirements, because our easements are not sufficient," 23 in that case. But that isn't the case in the situation. 24 MR. McARTHUR: Well, I won't explore that with 25 you if you feel uncomfortable with my questions and 26 answering them. I was just trying to find out whether 27 there had been any change in the policy in recent times 28 with respect to existing easements. 95 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 MR. MARCELLO: I think my answer was I am not 2 aware of formal policy. But the practice would have 3 been -- or my understanding of the practice is that if 4 we require additional easements definitely we will be 5 talking to the landowners to negotiate those; and if we 6 do not, then we would be informing landowners of what we 7 are doing, just as we have done through this 8 environmental assessment process. 9 MR. McARTHUR: Yes, I understand about 10 additional easements. Obviously, if you needed 11 additional easements and additional lands you would 12 certainly be going to landowners. But I am just -- what 13 I am trying to find out is whether there was a policy 14 with respect to construction changes within an existing 15 easement. 16 MR. MARCELLO: I personally don't know, but -- 17 THE PRESIDING MEMBER: I think he has answered 18 your question: He doesn't know. 19 MR. McARTHUR: Those are all the questions I 20 have, Madam Chair. 21 THE PRESIDING MEMBER: Thank you, 22 Mr. McArthur. 23 Mr. Budd, I understand you have no questions. 24 MR. BUDD: None. Thank you. 25 THE PRESIDING MEMBER: Mr. Greenspoon -- now 26 that I can see you! 27 MR. GREENSPOON: Thank you. 28 MR. THOMPSON: Madam Chair, just if I might 96 HYDRO ONE NETWORKS PANEL 1, ex (McArthur) 1 precede my friend. When he finishes, it might make 2 sense for me to ask my questions on these easements, 3 because they do follow right along with Mr. McArthur, 4 and so that we would have it all at one place in the 5 record, rather than deferring it to Panel 3, but I am in 6 your hands. 7 THE PRESIDING MEMBER: How long do you think 8 your questions will last, Mr. Thompson? 9 MR. THOMPSON: Ten minutes. 10 THE PRESIDING MEMBER: Okay. Thank you. 11 Mr. Greenspoon. 12 MR. GREENSPOON: Yes, thank you. 13 EXAMINATION 14 MR. GREENSPOON: I just have a few questions. 15 My interest, just for your edification, Panel, is -- I 16 represent Northwatch. Northwatch is a coalition of 17 environmental groups from Northern Ontario. So we are 18 interested in the impact of this application on Northern 19 Ontario. 20 I had a couple of clearing-up questions, for 21 my knowledge. 22 Exhibit B, Tab 3, Schedule 2 -- that is the 23 map of -- that is the map that is the big map up there 24 behind us. Yes. It doesn't show any 115 kV lines. 25 Is that correct? 26 DR. MACEDO: That is correct. What is shown 27 there are the 230 and 500 kV lines. 28 MR. GREENSPOON: Does Hydro One consider 97 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 115 kV as part of the transmission system? 2 DR. MACEDO: Yes, it does. 3 MR. GREENSPOON: The 500 kilovolt construction 4 from Hamner to Mississauga, is that built? 5 DR. MACEDO: There is no 500 kV between Hamner 6 and Mississauga. There is a line that is built to 7 500 kV standards, but it is not energized at 500 kV. 8 MR. GREENSPOON: I see. So there is a 500 kV 9 line but it was built and it hasn't been used. 10 DR. MACEDO: Well, it is being operated at 11 230 kilovolts. 12 MR. GREENSPOON: At 230. Okay. 13 I see on that same map that there are four 14 other connections to Quebec, four other interconnects: 15 one at Dymond, one at Ottoholden, one at Chenaux, and 16 one at Chats Falls. 17 DR. MACEDO: Yes, that is correct. 18 MR. GREENSPOON: Those are the interconnects 19 that you describe as not being permanent. Is that the 20 word you used? 21 DR. MACEDO: That is correct. 22 MR. GREENSPOON: Did you look at any of those 23 interconnects as possible interconnects for this 24 project? 25 MR. MARCELLO: I'm sorry. Could you just 26 repeat the question. 27 MR. GREENSPOON: There are four northeasterly 28 interconnects to Quebec, four other ones. 98 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 MR. MARCELLO: That is correct. 2 MR. GREENSPOON: Were those looked at as an 3 alternative to this interconnect? 4 MR. MARCELLO: No, they were not. 5 MR. GREENSPOON: Will this interconnect have 6 any impact on those interconnects? 7 MR. MARCELLO: Once again I think the 8 interconnections are there and the facilities will be 9 used in any manner that the market dictates. If it is 10 economic to do so, they will continue to be used in that 11 manner. I don't know how the world is going to play out 12 in terms of the market, but the interconnections are 13 there. Generators can be isolated from one system to 14 the other and back. It is my expectation that that 15 would continue into the future. 16 MR. GREENSPOON: Would it be your expectation 17 that some of these, one or more of these four 18 interconnects, could perhaps be the subject of an 19 application at a later date for a permanent 20 interconnect? 21 DR. MACEDO: I doubt it. The Quebec system on 22 the other side is fairly weak and it is very unlikely, 23 in my view, that those interconnects, those connection 24 points would be converted into a permanent 25 interconnection. 26 MR. GREENSPOON: If we could turn to the other 27 map then, Tab 2, Schedule 3, page 1, that is the 28 specific site map of the interconnect. Do you have 99 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 that? 2 MR. MARCELLO: Yes. 3 MR. GREENSPOON: Now, I wondered what those 4 little red lines, those two red lines coming -- going to 5 the south and east out of the Hawthorne Station were? 6 I think your big map is on the floor if you 7 are looking for it. They don't appear to be on it. 8 MR. MARCELLO: Basically coming out of 9 Ottawa-Hawthorne there are two 500 kV lines that are 10 working into Ottawa. 11 MR. GREENSPOON: So then the key on the 12 schedule is wrong. Where it says "Red is Quebec 13 interconnection circuits," the two red lines going south 14 and east from Hawthorne are not Quebec interconnect. Is 15 that right? 16 MR. MARCELLO: I would say that -- that is 17 correct. Yes, that is an error. 18 MR. GREENSPOON: So those two red lines are 19 500 kV lines. Is that what your guess is? 20 MR. MARCELLO: Without looking at the whole -- 21 a bigger system map, I would say that there are -- that 22 is possible, yes. But they are definitely not the Hydro 23 Quebec interconnection. That would end at Hawthorne. 24 MR. GREENSPOON: At Hawthorne. Thank you. 25 And those blue lines on that same map, those 26 are the 115 kV's that we are talking about not being on 27 the system map. The other map we looked at earlier, the 28 bigger province map. 100 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 MR. MARCELLO: That is correct. Yes. 2 MR. GREENSPOON: And do those feed off the -- 3 say for example, at Gamble Junction, do those feed off 4 the Quebec interconnect circuit? 5 MR. MARCELLO: No, they do not. 6 MR. GREENSPOON: No. 7 MR. MARCELLO: The Quebec -- the proposed 8 interconnection is going to run from Outaouais straight 9 to Hawthorne without any stations or loads tapped off. 10 MR. GREENSPOON: Right. 11 MR. MARCELLO: It is, for all intents and 12 purposes, an express connection. 13 MR. GREENSPOON: Except for Masson and 14 Maclaren. 15 MR. MARCELLO: Even there -- even there there 16 is not a connection to the Hydro Quebec interconnected 17 circuits. 18 MR. GREENSPOON: Where is the HVAC situated? 19 That is the -- the HVAC is the inverter or the 20 converter. 21 MR. MARCELLO: The converter equipment will be 22 located at the Hydro Quebec Outaouais substation which 23 is shown on that drawing you are referring to basically 24 at the top of the page. 25 MR. GREENSPOON: I see. So it is going over 26 from Ontario as AC? 27 MR. MARCELLO: That is correct. At Outaouais 28 the DC, the high voltage DC equipment will take the AC 101 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 from the Hydro Quebec system, convert it to DC and back 2 to AC all within the Outaouais station. 3 MR. GREENSPOON: And what is the line loss at 4 that HVAC, do you know? 5 MR. MARCELLO: I'm sorry? 6 MR. GREENSPOON: What is the line loss, the 7 voltage loss that is lost to equipment at the HVAC? In 8 other words, for every volt of AC that we send from 9 Ontario how many volts do they get after the HVAC 10 conversion and inversion at Quebec? 11 DR. MACEDO: I may try to answer this. 12 If the voltage received at the converter 13 station is 230 kV and if it is converted back into 14 230 kV AC, there is no volt drop -- there is no volt 15 drop at -- yes. I'm sorry, my colleague is telling me 16 that the Outaouais is 315 kV. 17 There is no volt drop in the converter 18 station. The converter station requires certain 19 reactive support in order to make it work. And both 20 Hydro Quebec and ourselves, we would be putting in 21 reactive support to make sure that the converter is fed 22 with the right support so that it can operate in an 23 efficient manner. 24 MR. GREENSPOON: Yes. But I understand you 25 are converting from 230 to 315 and in the middle you are 26 converting to DC. When you convert to DC you lose some 27 power. There is some inefficiency in conversion and 28 then inversion. Is that not correct? 102 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 DR. MACEDO: The equipment is back-to-back. 2 There is a conversion that takes place. The losses in 3 the converter station is very, very small. 4 MR. GREENSPOON: Do you know what it is? 5 DR. MACEDO: I don't know what it is but the 6 person who is going to be on Hydro Quebec will tell you 7 what that loss is. They are very small. 8 MR. GREENSPOON: All right. Fine. Thank you. 9 With respect to the markets in Quebec and who 10 may be bidding on those markets once we have open 11 access, are those questions for Panel 2 or are those 12 questions that I should be asking? 13 DR. MACEDO: Yes, they are for Panel 2. 14 MR. GREENSPOON: With respect to -- if you 15 look again at the big map, Tab 3, Schedule 2, page 1, in 16 that -- in that insert we have what is called the West 17 System. In that map there is an insert called the West 18 System. 19 DR. MACEDO: That is correct. 20 MR. GREENSPOON: Now, there are two -- there 21 are two generators in that area, are there not? Two 22 stations. Are you aware of -- you have been at Hydro 23 for a long time, you are aware of the system? 24 DR. MACEDO: Yes, I am. 25 MR. GREENSPOON: All right. And up in there 26 we have Atikokan and Thunder Bay. 27 DR. MACEDO: Yes, they are the fossil plants. 28 MR. GREENSPOON: Those are two fossil plants 103 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 and those are -- those remain unscrubbed to your 2 knowledge? 3 DR. MACEDO: I really should restrict my 4 comments to Hydro One assets. The question you are 5 asking me really are more relevant for the generating 6 company to respond to. 7 MR. GREENSPOON: Yes, but you know as a fact 8 when you were at Hydro that these are the only two 9 unscrubbed fossil generating stations in Ontario? 10 DR. MACEDO: Really I don't want to speak on 11 behalf of OPG. 12 MR. GREENSPOON: Okay. All right. 13 Can you -- then hypothetically would you 14 accept that they are unscrubbed, just for the purpose of 15 my next question? 16 Assuming that they are unscrubbed, subject to 17 your finding out that they have scrubbed -- they are 18 scrubbed, and I think it is on the record at other 19 hearings, Madam Chair, that these are two unscrubbed 20 fossil stations -- was it a consideration of the 21 transmission company that an interconnection to 22 Minnesota might have taken some of the pressure off of 23 those two stations and that perhaps that area of Ontario 24 wouldn't be ready -- wouldn't be subject to unscrubbed 25 fossil burning if the interconnect had been with 26 Minnesota? 27 DR. MACEDO: We do have an interconnection 28 with Minnesota. 104 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 MR. GREENSPOON: A permanent interconnection? 2 DR. MACEDO: A permanent interconnection. 3 MR. GREENSPOON: All right. And how many 4 megawatts is that? 5 DR. MACEDO: That I believe is 100 megawatts, 6 150 megawatts. I can't remember the details. 7 MR. GREENSPOON: All right. And this 8 application is how many megawatts? 9 DR. MACEDO: It's 1250. 10 MR. GREENSPOON: So 1200. So it's one-tenth? 11 DR. MACEDO: Yes. 12 MR. GREENSPOON: So presumably if more 13 interconnect was established at Minnesota, less 14 interconnect would be needed to meet the OEB's suggested 15 target? 16 DR. MACEDO: We did look at all the 17 interconnections, all the opportunities across the 18 province and we did look at the Minnesota 19 interconnection. 20 MR. GREENSPOON: Yes. 21 DR. MACEDO: The cost to upgrade the Minnesota 22 interconnection is new unit cost, in other words, the 23 dollars per megawatt for the upgrade is far greater than 24 the cost for the Hydro Quebec upgrade. And the other 25 very important thing to bear in mind is that in order to 26 make full use of any capacity that you provided 27 interconnection, you have to look at the transmission 28 system beyond the interconnection itself and in 105 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 Minnesota we would have to upgrade a major interface 2 which we call the east/west interface which goes between 3 Wawa and Marathon and the cost of upgrading that has to 4 be taken into account. 5 So when you take both the upgrade of the 6 interconnection itself plus the upgrade of the interface 7 required to make use of that interconnection, the unit 8 cost does not compare with the Hydro Quebec option. 9 MR. GREENSPOON: But that again was not taking 10 into account any environmental impacts of unscrubbed 11 fossil generation. That was not part of your 12 consideration? 13 DR. MACEDO: That was not part of the 14 consideration, no. 15 MR. MARCELLO: I think there is an important 16 point to add here. 17 For an interconnection to work you need two 18 parties and in this case we have Hydro Quebec. With 19 Minnesota, we have been discussing and studying 20 possibilities for expanding that interconnection for 21 many years and although there is lots of good will in 22 terms of looking at options and studies, when it really 23 comes down to it, the drivers are not there for either 24 party. 25 I think Dr. Macedo alluded to the high cost on 26 our end and from the Minnesota perspective, they also 27 had concerns. 28 MR. GREENSPOON: Just one last area and that 106 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 is the actual transfer of power from the west system to 2 the east system. 3 What is your understanding of that? Is there 4 a net flow one way or the other? 5 DR. MACEDO: No, there isn't. Power flows in 6 both directions. 7 MR. GREENSPOON: And what about at Hamner? Is 8 there a flow north and south or -- 9 DR. MACEDO: Again, same thing. Power flows 10 both north and south, depending upon the time of day. 11 MR. GREENSPOON: And would you say it nets out 12 at zero at those two systems? 13 DR. MACEDO: I haven't looked at them recently 14 but I would say yes, close. 15 MR. GREENSPOON: That seems to be what it -- 16 that is what it was at the DSP -- at the time of the 17 Demand Supply Plan, wasn't it? 18 DR. MACEDO: That's right. 19 MR. GREENSPOON: Yes. And will this 20 interconnect impact on those flows, this interconnect 21 that is the subject of this application? It could. 22 DR. MACEDO: It could. 23 MR. GREENSPOON: Yes. 24 Thank you. Those are all the questions I 25 have. 26 THE PRESIDING MEMBER: Thank you very much, 27 Mr. Greenspoon. 28 Mr. Brown, you have no questions, as I 107 HYDRO ONE NETWORKS PANEL 1, ex (Greenspoon) 1 remember. 2 Mr. Thompson, you have 10 minutes. 3 MS ALDRED: I just wanted to point out one 4 more time and I will leave it in your hands, of course, 5 that Mr. McCormick -- well, he has got more detailed 6 knowledge. 7 MR. THOMPSON: Yes, I understand that, but I 8 understand that your second panel cannot start up today 9 so I thought it might be helpful to use a little time 10 here and it fits in with what Mr. McArthur was 11 questioning. So if I -- 12 THE PRESIDING MEMBER: You have ten minutes, 13 Mr. Thompson. And for the witnesses, if you cannot 14 answer Mr. Thompson's questions -- you can always defer 15 it to the others. 16 EXAMINATION 17 MR. THOMPSON: Panel, would you go back to 18 Cumberland's evidence at Tab 3, that page we were 19 looking at before with the tower designs, about four in. 20 THE PRESIDING MEMBER: I'm sorry, 21 Mr. Thompson. Which tab was this? 22 MR. THOMPSON: It is Tab 3, fourth page in, 23 and it is the page entitled "Hydro Quebec 24 Interconnection Existing and Proposed Tower Options". 25 THE PRESIDING MEMBER: Thank you. 26 MR. THOMPSON: Come on guys, you are eating 27 into my time. 28 --- Laughter 108 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: Can you find the page? 2 MR. MARCELLO: Okay, yes. 3 MR. THOMPSON: You got it? 4 MR. MARCELLO: Yes. 5 MR. THOMPSON: All right. 6 My understanding is that what is there now are 7 the two pictures shown on the top line on the right-hand 8 side. 9 MR. MARCELLO: Yes. 10 MR. THOMPSON: And they are 75 and 73 feet 11 high? 12 MR. MARCELLO: Yes. That is pretty typical. 13 I wouldn't want to leave the impression that every tower 14 is exactly that height. 15 MR. THOMPSON: Well, big picture. 16 MR. MARCELLO: Yes, big picture, that is it. 17 MR. THOMPSON: That is what we have running 18 through this easement. 19 What you are proposing to put there is down on 20 the bottom line, left corner. 21 MR. MARCELLO: Yes. 22 MR. THOMPSON: Right. And that is 152 -- what 23 is the height and what -- 24 MR. MARCELLO: I think it shows 162. 25 MR. THOMPSON: Right. 26 MR. MARCELLO: I believe that the actual 27 towers that will end up being built will range from 28 130 to 150 but Panel 3 can confirm that. 109 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: Okay. And the base is larger? 2 MR. MARCELLO: The base is -- 3 MR. THOMPSON: It's 28.5, I think. 4 MR. MARCELLO: Well, big picture, they are the 5 same. You know, 8.73 versus 8.07. But yes, I guess it 6 is bigger. 7 MR. THOMPSON: Precisely. They are not the 8 same and obviously they are different towers. 9 MR. MARCELLO: Yes, they are different towers. 10 MR. THOMPSON: So what you are doing really is 11 taking down existing towers. Right? 12 MR. MARCELLO: Yes. 13 MR. THOMPSON: And putting up new towers? 14 MR. MARCELLO: Yes. 15 MR. THOMPSON: Okay. And that is no 16 different -- whether they are your lattice design or 17 pole design, it is no different. You are taking down 18 existing and putting up new. 19 MR. MARCELLO: The difference in that scenario 20 is you have a lot more poles. 21 MR. THOMPSON: There are more steel poles, I 22 accept that. 23 MR. MARCELLO: Okay. 24 MR. THOMPSON: But you say you have a legal 25 opinion that you can do the first, take down existing 26 and put up new, larger towers carrying more lines 27 without additional easement rights. Did I understand 28 that correctly? 110 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. MARCELLO: That is correct, yes. 2 MR. THOMPSON: Is that an internal legal 3 opinion or is that external? 4 MS ALDRED: Well, I don't know that 5 confidential legal opinions are really -- 6 MR. THOMPSON: Fine. I won't debate that at 7 this point. 8 Now, you then say, as I understand it, and you 9 say this in this Exhibit 13.21, second last page, that 10 you will need additional easement rights to do the steel 11 pole option. 12 MR. MARCELLO: I don't have the exhibit in 13 front of me, but yes -- 14 MR. THOMPSON: Okay. 15 MR. MARCELLO: -- we do say that. 16 MR. THOMPSON: All right. Is that based on 17 some legal opinion? 18 MR. MARCELLO: It is my understanding, yes. 19 MR. THOMPSON: All right. 20 Your easements that Mr. McArthur referred you 21 to are not footprint specific. They cover the whole 22 hundred and whatever width it is. 23 MR. MARCELLO: I haven't read them so -- 24 MR. THOMPSON: Well, would you take that 25 subject to check that you have -- whatever rights you 26 have, you have over that entire width of property? 27 MR. MARCELLO: Are you asking me to clarify 28 what the easements give us rights to? 111 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: I am trying to have you explain 2 why you say your easements are in effect footprint 3 specific when they are not. 4 MR. MARCELLO: I didn't think I said the 5 easements were footprint specific. Maybe -- 6 MR. THOMPSON: Well, it must be saying that if 7 you are saying to do what you are proposing to do with 8 steel towers which involves putting up more, you need 9 more easement rights. Either you have the right to do 10 what you propose to do, take down old and put up new 11 through the entire width of the easement, or you don't. 12 If you have it, you can do what you are 13 proposing to do or the steel pole alternative without 14 further rights and if you don't, you can't do either 15 alternative without further rights. 16 MS ALDRED: This is still a legal conclusion, 17 I think. 18 MR. THOMPSON: All right, I will accept that. 19 It is a legal question and my question of the Hydro 20 Panel is: who should answer the question? Are you 21 expecting the Board to answer this question? 22 MR. MARCELLO: Again, this is not my area but 23 I think the OMB has jurisdiction on these sorts of 24 matters but that is just my understanding. 25 MR. THOMPSON: Well, can you help me with 26 process and maybe your lawyer can. 27 Where do we go if this Board agrees that this 28 is a legal question that needs to be resolved? It 112 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 affects your project costs and it obviously affects 2 timing. 3 MS ALDRED: Our position is that these 4 individual matters are not properly before the Board in 5 this matter. The OMB has jurisdiction over compensation 6 issues -- 7 THE COURT REPORTER: Ms Aldred. 8 MS ALDRED: I'm so sorry. I keep forgetting 9 the microphone. 10 Our position is that the OMB has jurisdiction 11 over these matters and that these concerns are not 12 properly before you. They either belong before the OMB 13 or if someone wants to allege that the easement rights 14 are not sufficient then that may be a matter for a court 15 application but it is not a matter for you to determine. 16 MR. THOMPSON: Okay. One last question, then. 17 In the Act, section 97, it reads: 18 "In an application under sections 90, 91 19 or 92, leave to construct shall not be 20 granted until the applicant satisfies the 21 Board that it has offered or will offer 22 to each owner of land affected by the 23 approved route or location, an agreement 24 in a form approved by the Board." 25 (As read) 26 Does that have anything to do with easement 27 rights? 28 MR. MARCELLO: I'm not familiar with that. 113 HYDRO ONE NETWORKS PANEL 1, ex (Thompson) 1 MR. THOMPSON: I will let your counsel take 2 that under advisement and perhaps put it on the record 3 once she has had a chance to consider it. 4 Thank you very much. 5 THE PRESIDING MEMBER: Thank you, 6 Mr. Thompson. 7 EXAMINATION 8 THE PRESIDING MEMBER: I just have one quick 9 question for clarification. 10 I know that there is now 400 megawatts of what 11 you call the emergency connection. Is this project 12 going to affect the ability for this 400 megawatts of 13 what you call emergency connection? 14 MR. MARCELLO: While we are constructing the 15 tie, that 400 megawatt connection is still there, but 16 there will come a point when we are cutting over, so to 17 speak, and putting this whole project in-service and 18 that 400 megawatt tie basically disappears. 19 We are reusing the facilities, the line 20 facilities from Outaouais to the river crossing that 21 currently provide that 400 megawatt tie. They will be 22 integrated into Hydro Quebec's portion of this 1,250 23 tie. So once the project is in service, that 24 400 essentially disappears. 25 MS HALLADAY: So will the capacity of the 26 other interconnects to Quebec provide this, what you 27 call emergency interconnection, or will that not be 28 necessary with the new interconnect? 114 HYDRO ONE NETWORKS PANEL 1, ex (Halladay) 1 MR. MARCELLO: It will be made redundant by 2 this 1,250 megawatt tie. 3 Basically what happened, after the ice storm 4 this area was one of the areas that was hit particularly 5 hard in Quebec. This interconnection, this tie was 6 proposed. It was put in very quickly and it is there to 7 provide just that kind of emergency support. 8 Once these facilities are fully in place, the 9 1,250 megawatt tie, Hydro Quebec's Outaouais area will 10 have been reinforced. So again, their primary driver 11 for the project has been "improve the reliability" and I 12 think the ice storm was a catalyst in pushing the 13 project on their end. 14 On our end, the whole evolving market and 15 market conditions was the driver. So the two things 16 came together at the right time and two willing partners 17 got together and this is the proposal we have now. 18 MS HALLADAY: One other question. 19 The conversion equipment is going to be at 20 Outaouais. Is there any concern about a system 21 reliability with it being outside the jurisdiction of 22 Networks? 23 MR. MARCELLO: Not at all. The equipment 24 in -- well, first off, I think Hydro Quebec can comment 25 a lot more on the third panel about their experience 26 with the equipment. They have a lot of connections with 27 New England and New York and a lot of experience in 28 using that equipment. 115 HYDRO ONE NETWORKS PANEL 1, ex (Halladay) 1 In effect, what has happened is any event on 2 either side is, in effect, buffered by that equipment. 3 So when we are doing our studies for NPCC -- and the IMO 4 is basically repeating a lot of these studies -- what 5 happens is you have to take into account what if this 6 interconnection were to disappear and what would that do 7 to the system? And the system has to stay together in 8 the event of a contingency. 9 So from an overall reliability point of view, 10 you have a buffer. If something happens in Quebec, it 11 doesn't transfer in Ontario. If something happens in 12 Ontario, it doesn't transfer into Quebec. 13 If there is a problem with the buffer itself, 14 the system is designed to withstand that. And I think 15 it is one of the basic criteria NPCC looks at and it is 16 one of the reasons we do a lot of analysis in that area, 17 and we have been working with the IMO as well to make 18 sure that the system is robust and it stays together and 19 this thing works the way it should. 20 DR. MACEDO: I know that he has explained it, 21 but if I can just sort of summarize. 22 The system, both the Quebec system and our 23 system, is designed and operated to be able to withstand 24 the loss of that convertor and in order to be able to do 25 that you have to put in facilities to allow you to be 26 able to withstand that. And that is one of the main 27 contingencies that the IMO will be looking at as part of 28 the system impact study, among others. 116 HYDRO ONE NETWORKS PANEL 1, ex (Halladay) 1 If I may just add one more point, and that is 2 that we have done a tremendous amount of studies on this 3 interconnection. We have prepared umpteen reports. We 4 have submitted this to the NPCC. In fact, it was 5 discussed only last Thursday at the Task Force on 6 Systems Studies where the group, which includes the IMO, 7 Hydro Quebec, New England, all the other players, 8 examined this and they found no major concerns as to 9 what we were proposing. 10 Based on all these sorts of studies, we have 11 come up with a very -- we have determined what 12 facilities we needed, and we are fairly confident, in 13 fact very confident that what we proposed in fact will 14 meet the test that the IMO will be carrying out. 15 THE PRESIDING MEMBER: Thank you, Dr. Macedo. 16 Are there any other questions from the 17 intervenors? 18 Anything on redirect? 19 MS ALDRED: I did have one question and it 20 just follows on the last point that Dr. Macedo was 21 making. 22 EXAMINATION 23 MS ALDRED: I think it is Mr. Marcello, in 24 your testimony you mentioned that the actual contract 25 for the System Impact Assessment had not perhaps yet 26 been executed by the IMO. I'm just wondering, does that 27 mean that there has been no work done with the IMO on 28 this issue or has there been some carried out? 117 HYDRO ONE NETWORKS PANEL 1, ex (Aldred) 1 MR. MARCELLO: Not at all. We have been 2 working with the IMO since July/June specifically on the 3 project. We have been doing joint studies. Part of 4 their scope, in fact, is the accountability and the 5 responsibility of Hydro One Networks to undertake. The 6 interesting thing here is, we are a proponent. I think 7 when the process was designed it was anticipated that a 8 third party would come into their assessment and then 9 Hydro One could comment and do studies in that regard. 10 In this case we are the proponent, so those studies have 11 been done. 12 I think just to characterize it, we have been 13 working together, we have been working along, but 14 because it is a new process and there have been some 15 administrative hiccups, a contract hasn't been signed. 16 The cheque is in the mail, so to speak -- and it is, by 17 the way. 18 MS ALDRED: That was all my re-direct. 19 Thank you. 20 THE PRESIDING MEMBER: Thank you. 21 Dr. Macedo, Mr. Marcello, you are excused, 22 with our thanks. Thank you very much. 23 Mr. Brown, I understand you have a statement 24 you would like to make? Is now an appropriate time for 25 you to state your statement? 26 MR. BROWN: Perhaps after lunch would be more 27 appropriate, Madam Chair. 28 THE PRESIDING MEMBER: Now, I understand that 118 1 we are not going to have the next panel after lunch. Is 2 that correct? 3 MS ALDRED: Yes, that is correct. I'm sorry, 4 I have a scheduling difficulty with one of our witnesses 5 from out of town actually, and so I appreciate your 6 indulgence until tomorrow morning for the second panel. 7 THE PRESIDING MEMBER: Mr. Brown, how long 8 will your statement be for us to reconvene after lunch 9 just to hear your statement? 10 MR. BROWN: Well, no. Under that 11 circumstance, I suggest we defer until tomorrow morning. 12 I just have to consult with a few people so I would 13 just -- 14 THE PRESIDING MEMBER: I appreciate that. I 15 didn't want to pressure you to make a statement. I am 16 just trying to fit it all in. 17 That being said, I think that we are now 18 adjourned until tomorrow morning at 9:30, at which time 19 we will hear Panel No. 2. 20 Thank you very much. 21 --- Whereupon the hearing adjourned at 1318, 22 to resume on Thursday, November 23, 2000 at 0930 23 24 25 26 27 28 119 1 INDEX OF PROCEEDING 2 PAGE 3 Upon commencing at 0940 3 4 Preliminary Matters 6 5 Motion by Mr. Klippenstein 7 6 Decision 12 7 Preliminary Matters 12 8 Opening statement by Ms Aldred 15 9 HYDRO ONE NETWORKS PANEL 1 10 SWORN: DR. FRANK MACEDO 18 11 SWORN: MR. CARMINE MARCELLO 18 12 Examination by Ms Aldred 18 13 Examination by Mr. Moran 39 14 Examination by Mr. Thompson 48 15 Upon recessing at 1123 64 16 Upon resuming at 1153 64 17 Examination by Mr. Klippenstein 64 18 Examination by Mr. McArthur 85 19 Examination by Mr. Greenspoon 96 20 Examination by Mr. Thompson 107 21 Examination by The Board 113 22 Examination by Ms Aldred 116 23 Upon adjourning at 1318 118 24 25 26 27 28 120 1 EXHIBITS 2 NO. DESCRIPTION PAGE 3 14.1 Supplementary Interrogatories 13 4 filed by Hydro One 5 6 14.2 Curriculum vitae of Hydro 14 7 One's witnesses 8 9 14.3 Document entitled "Serving Our 70 10 Customers Better" Strategic Plan 11 2000-2004 12 13 14.4 Document entitled "The Loop" 70 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 121 1 UNDERTAKINGS 2 3 NO. DESCRIPTION PAGE 4 5 15.1 Dr. Macedo undertakes to provide 58 6 information on steel pole use for 7 Panel 3 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28