Wataynikaneyap Power LP 2022 Transmission Rates

EB-2021-0134

Wataynikaneyap Power LP is the owner and operator of a new transmission system that is being constructed in northwestern Ontario to reinforce part of the existing transmission system and to connect certain remote First Nations communities to the provincial electricity transmission system.

he new transmission system comprising the Line to Pickle Lake and Remote Connections Lines is expected to come into service in stages, in 2022 and 2023. The Line to Pickle Lake is expected to come into service in April 2022, and the initial segments of the Remote Connection Lines are expected to come into service between April and October 2022.

Wataynikaneyap Power LP has applied to the Ontario Energy Board for approval to establish electricity transmission rates effective April 1, 2022, and to charge Hydro One Remote Communities Inc. a fixed charge effective May 1, 2022. If the application is approved as filed, the monthly bill of a typical residential customer in Ontario and a typical general service customer in Ontario would increase by the following amounts:

Residential 750 kWh $0.36 per month
General Service less than 50kW $0.97 per month

 

Any change to the provincial transmission rate will cause a change to the delivery line on all electricity bills for all electricity customers in Ontario – both residential and business.

Type
Rates
The above links will take you to our document repository

Details and Updates

The OEB has issued a Decision and Order on an Application for 2022 electricity transmission rates and other charges.

Submit a letter of comment

You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment must be received by the OEB no later than 60 days after the publication or service date of the notice for the application. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.

More about commenting and privacy

More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters can be seen at our offices and will be placed on our website. Before the letter of comment is placed on the public record, all personal (i.e. not business) contact information is removed, such as the individual's address, fax and phone numbers, and email address. The individual's name and the content of the letter will become part of the public record..

If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your contact information. The OEB removes your contact information from your letter for privacy reasons before it is posted to our website.Show less

This information will be visible on the OEB's public website.
Upload an attachment only if you need to submit additional information relating to your comment. Only PDF and Word files will be accepted.
Choose file
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Get updates about this application:

Or mail the below address with the reference number EB-2021-0134

Ontario Energy Board
P.O. Box 2319
2300 Yonge Street, 27th Floor
Toronto ON M4P 1E4
Attn: Registrar