EB-2025-0093
On September 4, 2025, the Ontario Energy Board (OEB) issued its Decision and Order on Hydro One Networks Inc.’s (Hydro One) application for authority to expropriate permanent corridor easements on five parcels of land to construct a 64-kilometer 230 kV transmission line in southwestern Ontario (St. Clair Transmission Project).
Secteur
Electricity
Requérant/problème
Hydro One Networks Inc.