Hydro One Networks Inc. (EB-2026-0254) - Leave to construct transmission line facilities in Brampton

Hydro One Networks Inc.
EB-2026-0254

Hydro One Networks Inc. (Hydro One Networks) has applied to the Ontario Energy Board (OEB) for leave to construct transmission line facilities in the Brampton area of southwest Ontario. The work involves the reconductoring of approximately 8.5 kilometres of an existing 230 kV transmission line between Hurontario Switching Station and Pleasant Transformer Station and requires minor reinforcement of the steel towers along the route (Project). Hydro One Networks says that the Project will improve the reliability and efficiency of the transmission system and provide sufficient capacity to meet expected electricity demand growth in the area.

Part of the cost of the Project would be paid through a capital contribution from Alectra Utilities Corporation and Hydro One Networks’ distribution business.

Hydro One Networks proposes to calculate the upfront capital contribution using a 40-year revenue horizon. Hydro One Networks is also seeking approval of the forms of land use agreements offered or to be offered to affected landowners.

The OEB approval for leave to construct is not the only approval required before a line can be built.

Environmental issues, or issues related to the Crown’s duty to consult Indigenous peoples, are not part of the OEB’s review unless there is a direct impact on price and the reliability and quality of electricity service.

A map of the proposed route for the transmission line is provided below:

Map of proposed transmission line

Type: Leave to Construct

This application will be heard using the Complex Electricity & Natural Gas performance standard (pdf). View an expanded timeline (pdf) of the procedural steps for this Leave to Construct application and read the Standard Issues List (pdf).

Find out more about OEB Performance Standards for Processing Applications and use the Application Planning Tool to assist you with an estimate of the milestones in this proceeding.

See the application notice 
See the application 
See all documents related to this application 
The above links will take you to our document repository

Participate

There are three ways to participate in the OEB hearing process: as an Intervenor, submitting a Letter of Comment or to Follow a Proceeding.

This table illustrates the different levels of participation. Find out more about participating in an OEB hearing, including becoming an intervenor.

Participation ActivitiesIntervenorLetter of CommentFollow a Proceeding
Receive OEB-issued documents by email
Submit a Letter of Comment
Listen to live broadcast of the oral hearing
Participate in oral hearing
Present Evidence
Respond to questions about evidence
Ask other parties to the proceeding questions
Provide argument

Submit a letter of comment

You can submit a letter of comment that will be considered by the panel deciding the application. Unless the notice states otherwise, your letter of comment will be accepted until the record of the proceeding is closed (which usually occurs with the filing of the applicant’s final reply argument). However, you are encouraged to submit your letter as early in the process as you can. Depending on timing of receipt of letters of comment, the applicant will typically provide a respond to the issues raised in those letters. Your letter will be provided directly to the panel of Commissioners who will be deciding whether the application is approved. The panel will consider your comments in reaching their decision. The panel will only be able to consider comments which relate to issues which are within the authority of the OEB and relevant to the issues being considered by the panel.

More about commenting and privacy
All letters of comment sent to the OEB are placed on the public record. This means the letters will be placed on our website. Before the letter of comment is placed on the public record, personal contact information contained in the address, phone number, and email address fields of this form is removed. The individual's name and the content of the letter will become part of the public record.

If you would like a response from the applicant, please send a copy of your letter directly to the applicant, including your personal contact information. The OEB removes your personal contact information from your letter for privacy reasons before it is posted to our website.

Add Your Letter of Comment

All information provided in the section below will be made publicly available on the OEB website, including whether artificial intelligence was used. Please do not include any personal contact information in this section.
Did you use generative artificial intelligence1 in developing this letter of comment?
1Generative artificial intelligence means computer systems that can independently create content based on user prompts. Examples of Generative artificial intelligence tools include ChatGPT, Google Gemini, or Microsoft Copilot.
Upload an attachment only if you need to submit additional information relating to your comment. Only PDF and Word files will be accepted. All information provided in the document you attach will be made publicly available and placed on the OEB website. Please do not include any personal contact information in your attached document.
Choose file
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Get updates about this application:

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Or mail the below address with the reference number EB-2026-0254

Ontario Energy Board
P.O. Box 2319
2300 Yonge Street, 27th Floor
Toronto ON M4P 1E4
Attn: Registrar