Date Issued
              Case #
              EB-2017-0182
          The OEB has issued its Decision and Order on the following applications:
- Application for leave to construct an electricity transmission line between Thunder Bay and Wawa, Ontario (EB-2017-0182);
- Application to upgrade existing transmission station facilities in the Districts of Thunder Bay and Algoma, Ontario (EB-2017-0194);
- Application for leave to construct an electricity transmission line between Thunder Bay and Wawa, Ontario (EB-2017-0364);
- Decision and Order
Sector
          Electricity
              Applicant/Issue
              Upper Canada Transmission, Inc.; Hydro One Networks Inc.