We hold ourselves accountable to those we serve. In fulfilment of that accountability, we are reporting on adjudicative performance through this dashboard.
Our Adjudicative Reporting Dashboard provides regulated entities with transparency into our adjudicative process, in particular the metrics and targets we set to measure the efficiency of our decision-making. First published in 2021, the dashboard is updated twice per year.
What follows is a summary of achievements against our adjudicative targets for Q1 and Q2 of Fiscal 2026-2027.
Current Report
Fiscal 2026-2027: Mid-Year Results (April 1, 2026, to September 30, 2026)
- The OEB issued 89 decisions in Q1 and Q2 of Fiscal 2026-2027 – 94% of panel decisions and 100% of Delegated Authority decisions were issued in accordance with the Total Cycle Time performance standards (the panel target is 85% while the Delegated Authority target is 95%).
- Of all decisions issued, 66% were issued more than 14 days in advance of the decision metric date.
- April 2026 was the month during which most decisions were issued by the OEB. Twenty-four decisions were issued this month, or 27% of all decisions.
Total Decisions Issued
The majority of decisions (74%) issued by the OEB were heard by Delegated Authority. This is consistent with historical trends.
71% of the decisions issued in Q1 and Q2 of Fiscal 2026-2027 were for applications related to electricity. This is consistent with historical trends.
54% of all the decisions issued were for Licence applications. Facilities comprised 25% of decisions, followed by Rates (18%) and Mergers, Amalgamations, Acquisitions and Divestitures (3%). These are consistent with historical trends.
Decision Issuance Spectrum
In addition to monitoring whether a decision is issued on time, the OEB also monitors the degree to which decisions were issued early or late relative to the Total Cycle Time decision metric date established by the applicable performance standard. This Decision Issuance Spectrum highlights the fact that 66% of decisions issued this reporting period were issued more than two weeks in advance of the Total Cycle Time metric date.
Key Documents
The OEB issues many documents aside from decisions each month. “Key Documents” refers to all other documents that are issued by the OEB but are not a final Decision and Order (e.g., Notice, Procedural Order, Letter to Industry, etc.). The OEB issued 37 Key Documents on average each month of Q1 and Q2 of Fiscal 2026-2027.
Average Time for Procedural Order No. 1 (PO#1), Decision Writing and Total Cycle
The OEB has committed to report on the performance of key application milestones for applications heard by panels of Commissioners for major application types. The three graphs below illustrate the performance for various application types relative to the performance standard for:
This graph provides the average time from receipt of a complete application to the issuance of PO#1 and compares this to the performance standard.
For Complex Facilities applications and cost-based Rates applications with a revenue requirement of less than $500 million (Rates: <$500M), the average time to issue PO#1 exceeded the performance standard. This was due to several electricity facilities applications that had preliminary matters that required extra consideration prior to issuing PO#1 (e.g., requests for no hearing, requests for non-standard procedural steps, and questions related to legislative interpretation).
This graph provides the average time from the close of the record to the issuance of the decision and compares this to the performance standard. Although the OEB missed the Decision Writing Time metric for one case within this reporting period, on average it met or exceeded its targets.
This graph provides the average time from a complete application to the issuance of the decision and compares it to the performance standard.
The average Total Cycle Time for the Facilities: Complex applications exceeded the metric days. This was primarily driven by decisions involving complex issues that required additional time for deliberation by panels of Commissioners.
Past Reports
- Fiscal 2025-2026: Final Results (April 1, 2025 to March 31, 2026)
- Fiscal 2025-2026: Mid-Year Results (April 1, 2025 to September 30, 2025)
- Fiscal 2024-2025: Final Results (April 1, 2024 to March 31, 2025)
- Fiscal 2024-2025: Q1 and Q2 Results (April 1, 2024 to September 30, 2024)
- Fiscal 2023-2024: Final Results (April 1, 2023 to March 31, 2024)
- Fiscal 2023-2024: Q1 and Q2 Results (April 1, 2023 to September 30, 2023)
- Fiscal 2022-2023 : Final Results (April 1, 2022 to March 31, 2023)
- Fiscal 2022-2023: Q1 and Q2 Results (April 1, 2022 to September 30, 2022)
- Fiscal 2021-2022 : Final Results (April 1, 2021 to March 31, 2022)
- Fiscal 2021-2022: Q1 and Q2 Results (April 1, 2021 to September 30, 2021)
Related Documents
- Chief Commissioner Letter to Industry (Apr 30, 2026) (pdf)
- Chief Commissioner Letter to Industry (Nov 3, 2025) (pdf)
- Chief Commissioner Letter to Industry (October 21, 2024) (pdf)
- Chief Commissioner Letter to Industry (April 18, 2024) (pdf)
- Chief Commissioner Letter to Industry (October 19, 2023) (pdf)
- Chief Commissioner Letter to Industry (April 20, 2023) (pdf)